Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular, as per design and shape for floors and roofs in 1:1½:3 (1 Cement : 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 10 mm nominal size derived from natural sources), including flush or deep ruled pointing at joints in Cement mortar 1:2 (1 Cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but, excluding the cost of reinforcement

Item number
5.36
Analysis basis
1.38 cum
Priced inputs
8
Derived rate
₹33,018.75/ CUM
D-01/RATE ANALYSISITEM 5.36

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.36 (Providing and placing in position precast reinforced cement concrete waffle units, square or rectangular, as per design and shape for floors and roofs in 1:1½:3 (1 Cement : 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 10 mm nominal size derived from natural sources), including flush or deep ruled pointing at joints in Cement mortar 1:2 (1 Cement : 2 Fine sand), making necessary holes of required sizes for carrying through service lines etc., providing steel hooks for lifting etc, form work in precasting, handling, hoisting, centering and erection complete for all floor levels but, excluding the cost of reinforcement) is derived from 8 priced inputs for 1.38 cum and works out to ₹33,018.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider a waffle 09. x 0.9 x 0.3m
  • Total area covered 4.548x3.636 = 16.54 sqm.
  • Cement concrete in 1 unit
  • Top 0.8x0.8x0.035 = 0.0224
  • Sides 2(0.8x0.265x0.0325) = 0.0138
  • 2(0.735x0.265x0.0325) = 0.0127
  • Total = 0.0489
  • Flange 4x0.85x0.05x0.035 = 0.0060
  • Total = 0.0549
  • Total = 0.069 cum.
  • Quantity for 20 such units = 1.38 cum.
  • (i) Shuttering and centring
  • Face in contact
  • 4x0.8x0.265 = 0.848
  • Inner 4x0.735x0.265 = 0.779
  • Top (inside) 1x0.735x0.735 = 0.540
  • Flange 4x0.9x0.035 = 0.126
  • Total = 2.293 sqm.
  • Quantity 20 such units 45.86 sqm.
  • Hooks for lifting
  • 2x1.5 = 3.0m
  • 4x0.01 = 0.04m
  • Total = 3.04m
  • @ 3kg per m-9.12Kg or 0.009 t = 9 kg
  • (iv) Transportation and erection labour for 20
  • units
  • (v) Cost of poining flush or deep ruled in cement mortar 1:2 (1 Cement : 2 fine sand)
  • Add for Fillets 25% = 0.0137
ANALYSIS OF RATES · ITEM 5.36DETAILS OF COST FOR 1.38 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 5.2.2 of SH : RCCRate as per item 5.2.2cum1.3810,852.9514,977.07
SUBRate as per item no 5.9.15 of SH : RCCRate as per item 5.9.15sqm45.86392.1517,984.00
SUBRate as per item no 10.2 of SH : Steel workRate as per item 10.2kg9133.701,203.30
9988MAT(iii) 10mm dia. Bolts 60mm long with nuts and washers 2x2 = 4 Nos. including carriage of boltsL.S.132.2729.51
9999MATSundriesL.S.79.952.27181.49
0126LABMason (for ornamental stone work) 1st classday1897.00897.00
0114LABBeldarday6736.004,416.00
SUBRate as per item no 13.35.1 of SH : FinishingRate as per item 13.35.1sqm16.54214.203,542.87
BUILD-UP TO RATE
TOTAL
43,231.24
Add 1 % Water charges on “W-A”
+55.24
TOTAL
43,286.48
Add GST on “X-A” (multiplying factor 0.2127)
+1,186.70
TOTAL
44,473.18
Add 15% CPOH on “Y-A”
+1,014.89
TOTAL
45,488.07
Add Cess @ 1% on “Z-A”
+77.81
Total for 20 units
45,565.88
Cost for 1.38 cum.
45,565.88
Cost for 1 cum.
33,018.75
SAY
₹33,018.75
D-02/SOURCEPRINTED PAGE 284
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
284

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 284. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.