Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Add for using extra cement in the items of design mix over and above the specified cement content therein

Item number
5.35
Analysis basis
Details of cost for 1 quintal
Priced inputs
1
Derived rate
733.50 / quintal

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.35 Add for using extra cement in the items of design mix over and above the specified cement content therein — is derived from 1 priced inputs for 1 quintal and works out to ₹733.50 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.15,156.00515.60
TOTAL
515.60
Add 1 % Water charges on “W”
5.16
TOTAL
520.76
Add GST on “X” (multiplying factor 0.2127)
110.77
TOTAL
631.53
Add 15% CPOH on “Y”
94.73
TOTAL
726.26
Add Cess @ 1% on “Z”
7.26
Cost per quintal
733.52
Say
733.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 283. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works