Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.3
Analysis basis
1 cum
Priced inputs
11
Derived rate
₹11,505.50/ CUM
D-01/RATE ANALYSISITEM 5.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.3 (Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 11 priced inputs for 1 cum and works out to ₹11,505.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Extra labour for lifting material upto floor V
  • level:
  • Coolie (2.0x0.75=1.50)
ANALYSIS OF RATES · ITEM 5.3DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.571,425.00812.25
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.281,400.00392.00
0982MATCoarse sand (zone III)cum0.4251,450.00616.25
0367MATPortland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)tonne0.45,156.002,062.40
0155LABMason (average)day0.24857.00205.68
0114LABBeldarday2.75736.002,024.00
0101LABBhistiday0.9816.00734.40
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.08900.0072.00
0012MACHVibrator(Needle type 40mm)Vibrator (Needle type 40 mm)day0.08400.0032.00
9999MATSundriesL.S.14.32.2732.46
0115LABCoolieday1.5736.001,104.00
BUILD-UP TO RATE
TOTAL
8,087.44
Add 1 % Water charges on “W”
+80.87
TOTAL
8,168.31
Add GST on “X” (multiplying factor 0.2127)
+1,737.40
TOTAL
9,905.71
Add 15% CPOH on “Y”
+1,485.86
TOTAL
11,391.57
Add Cess @ 1% on “Z”
+113.92
Cost for 1 cum.
11,505.49
SAY
₹11,505.50
D-02/SOURCEPRINTED PAGE 209
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
209

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 209. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.