Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.3
Analysis basis
Details of cost for 1 cum.
Priced inputs
11
Derived rate
11,505.50 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.3 Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 11 priced inputs for 1 cum and works out to ₹11,505.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Extra labour for lifting material upto floor V
  • level:
  • Coolie (2.0x0.75=1.50)
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.571,425.00812.25
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.281,400.00392.00
0982Coarse sand (zone III)Materialcum0.4251,450.00616.25
0367Portland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)Materialtonne0.45,156.002,062.40
0155Mason (average)Labourday0.24857.00205.68
0114BeldarLabourday2.75736.002,024.00
0101BhistiLabourday0.9816.00734.40
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.08900.0072.00
0012Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machineryday0.08400.0032.00
9999SundriesMaterialL.S.14.32.2732.46
0115CoolieLabourday1.5736.001,104.00
TOTAL
8,087.44
Add 1 % Water charges on “W”
80.87
TOTAL
8,168.31
Add GST on “X” (multiplying factor 0.2127)
1,737.40
TOTAL
9,905.71
Add 15% CPOH on “Y”
1,485.86
TOTAL
11,391.57
Add Cess @ 1% on “Z”
113.92
Cost for 1 cum.
11,505.49
Say
11,505.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 209. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works