CPWD Analysis of Rates · Reinforced Cement Concrete

Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral staircases above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.3A
Analysis basis
Details of cost for 1 cum
Priced inputs
14
Derived rate
11,334.70 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.3A Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral staircases above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 14 priced inputs for 1 cum and works out to ₹11,334.70 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • Extra labour for lifting material upto floor V
  • level:Coolie (2.0x0.75=1.50)
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.4561,425.00649.80
0279Recycled Concrete Aggregate (RCA) 20 mm nominal sizeMaterialcum0.114957.00109.10
0297Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.2241,400.00313.60
0281Recycled Concrete Aggregate (RCA) 10 mm nominal sizeMaterialcum0.056957.0053.59
0982Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III)Materialcum0.341,450.00493.00
0278Manufactured sand derived from Recycled Concrete Aggregate (RCA)Materialcum0.085957.0081.35
0367Portland Cement (0.2833cum)Portland Cement (OPC-43 Grade)Materialtonne0.45,156.002,062.40
0155Mason (average)Labourday0.24857.00205.68
0114BeldarLabourday2.75736.002,024.00
0101BhistiLabourday0.9816.00734.40
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.08900.0072.00
0012Vibrator (Needle type 40 mm)Machineryday0.08400.0032.00
9999SundriesMaterialL.S.14.32.2732.46
0115CoolieLabourday1.5736.001,104.00
Total
7,967.38
Add 1 % Water charges on “W”
79.67
TOTAL
8,047.05
Add GST on “X” (multiplying factor 0.2127)
1,711.61
TOTAL
9,758.66
Add 15% CPOH on “Y”
1,463.80
TOTAL
11,222.46
Add Cess @ 1% on “Z”
112.22
Cost of 1 cum
11,334.68
Say
11,334.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 209. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works