Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement

1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
Item number
5.2.2A
Analysis basis
10x9.18 cum
Priced inputs
17
Derived rate
₹10,682.15/ CUM
D-01/RATE ANALYSISITEM 5.2.2A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.2.2A (Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 17 priced inputs for 10x9.18 cum and works out to ₹10,682.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • Extra labour for lifting of material upto floor V
  • level: 0.75x2.0x91.8=137.7
ANALYSIS OF RATES · ITEM 5.2.2ADETAILS OF COST FOR 10X9.18 CUM =91.80 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal sizecum41.861,425.0059,650.50
0279MATRecycled Concrete Aggregate (RCA) 20 mm nominal sizecum10.466957.0010,015.96
0297MATStone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal sizecum20.5631,400.0028,788.20
0281MATRecycled Concrete Aggregate (RCA) 10 mm nominal sizecum5.141957.004,919.94
0982MATCoarse sand (zone III) derived from natural sourcesCoarse sand (zone III)cum31.2121,450.0045,257.40
0278MATManufactured sand derived from Recycled Concrete Aggregate (RCA)cum7.803957.007,467.47
0367MATPortland Cement (0.2833cum)Portland Cement (OPC-43 Grade)tonne36.725,156.001,89,328.32
0114LABBeldarday112.9736.0083,094.40
0115LABCoolieday75.3736.0055,420.80
0101LABBhistiday82.6816.0067,401.60
0123LABMason 1st classMason 1st classday9.2897.008,252.40
0124LABMason (brick layer) 2 nd classMason 2nd classday9.2816.007,507.20
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday6.4900.005,760.00
0012MACHVibrator (Needle type 40 mm)day6.4400.002,560.00
9999MATSundriesL.S.1,318.22.272,992.31
9999MATScaffoldingL.S.4,200.32.279,534.68
0115LABCoolieday137.7736.001,01,347.20
BUILD-UP TO RATE
Total
6,89,298.38
Add 1 % Water charges on “W”
+6,892.98
TOTAL
6,96,191.36
Add GST on “X” (multiplying factor 0.2127)
+1,48,079.90
TOTAL
8,44,271.26
Add 15% CPOH on “Y”
+1,26,640.69
TOTAL
9,70,911.95
Add Cess @ 1% on “Z”
+9,709.12
Cost of 91.80 cum
9,80,621.07
Cost of 1 cum
10,682.15
SAY
₹10,682.15
D-02/SOURCEPRINTED PAGE 208
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
208

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 208. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.