Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement
- Item number
- 5.2.2A
- Analysis basis
- 10x9.18 cum
- Priced inputs
- 17
- Derived rate
- ₹10,682.15/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.2.2A (Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 17 priced inputs for 10x9.18 cum and works out to ₹10,682.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- Extra labour for lifting of material upto floor V
- level: 0.75x2.0x91.8=137.7
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal size | cum | 41.86 | 1,425.00 | 59,650.50 |
| 0279 | MAT | Recycled Concrete Aggregate (RCA) 20 mm nominal size | cum | 10.466 | 957.00 | 10,015.96 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal size | cum | 20.563 | 1,400.00 | 28,788.20 |
| 0281 | MAT | Recycled Concrete Aggregate (RCA) 10 mm nominal size | cum | 5.141 | 957.00 | 4,919.94 |
| 0982 | MAT | Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III) | cum | 31.212 | 1,450.00 | 45,257.40 |
| 0278 | MAT | Manufactured sand derived from Recycled Concrete Aggregate (RCA) | cum | 7.803 | 957.00 | 7,467.47 |
| 0367 | MAT | Portland Cement (0.2833cum)Portland Cement (OPC-43 Grade) | tonne | 36.72 | 5,156.00 | 1,89,328.32 |
| 0114 | LAB | Beldar | day | 112.9 | 736.00 | 83,094.40 |
| 0115 | LAB | Coolie | day | 75.3 | 736.00 | 55,420.80 |
| 0101 | LAB | Bhisti | day | 82.6 | 816.00 | 67,401.60 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 9.2 | 897.00 | 8,252.40 |
| 0124 | LAB | Mason (brick layer) 2 nd classMason 2nd class | day | 9.2 | 816.00 | 7,507.20 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 6.4 | 900.00 | 5,760.00 |
| 0012 | MACH | Vibrator (Needle type 40 mm) | day | 6.4 | 400.00 | 2,560.00 |
| 9999 | MAT | Sundries | L.S. | 1,318.2 | 2.27 | 2,992.31 |
| 9999 | MAT | Scaffolding | L.S. | 4,200.3 | 2.27 | 9,534.68 |
| 0115 | LAB | Coolie | day | 137.7 | 736.00 | 1,01,347.20 |
- Total
- 6,89,298.38
- Add 1 % Water charges on “W”
- +6,892.98
- TOTAL
- 6,96,191.36
- Add GST on “X” (multiplying factor 0.2127)
- +1,48,079.90
- TOTAL
- 8,44,271.26
- Add 15% CPOH on “Y”
- +1,26,640.69
- TOTAL
- 9,70,911.95
- Add Cess @ 1% on “Z”
- +9,709.12
- Cost of 91.80 cum
- 9,80,621.07
- Cost of 1 cum
- 10,682.15
- SAY
- ₹10,682.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 208
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 208. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.