CPWD Analysis of Rates · Reinforced Cement Concrete

Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement

1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.2.2
Analysis basis
Details of cost for 10x9.18 cum =91.80 cum
Priced inputs
14
Derived rate
10,852.95 / x9.18 cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.2.2 Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 14 priced inputs for 10x9.18 cum and works out to ₹10,852.95 per x9.18 cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Extra labour for lifting of material upto floor V
  • level:
  • 0.75x2.0x91.80 = 137.7
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum52.3261,425.0074,564.55
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum25.7041,400.0035,985.60
0982Coarse sand (zone III)Materialcum39.0151,450.0056,571.75
0367Portland Cement (0.2833 cum)Portland Cement (OPC-43 Grade)Materialtonne36.725,156.001,89,328.32
0114BeldarLabourday112.9736.0083,094.40
0115CoolieLabourday75.3736.0055,420.80
0101BhistiLabourday82.6816.0067,401.60
0123Mason 1st classMason 1st classLabourday9.2897.008,252.40
0124Mason 2nd classMason 2nd classLabourday9.2816.007,507.20
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday6.4900.005,760.00
0012Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machineryday6.4400.002,560.00
9999SundriesMaterialL.S.1,318.22.272,992.31
9999ScaffoldingMaterialL.S.4,200.32.279,534.68
0115CoolieLabourday137.7736.001,01,347.20
TOTAL
7,00,320.81
Add 1 % Water charges on “W”
7,003.21
TOTAL
7,07,324.02
Add GST on “X” (multiplying factor 0.2127)
1,50,447.82
TOTAL
8,57,771.84
Add 15% CPOH on “Y”
1,28,665.78
TOTAL
9,86,437.62
Add Cess @ 1% on “Z”
9,864.38
Cost for 91.80 cum.
9,96,302.00
Cost for 1 cum.
10,852.96
Say
10,852.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 207. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.