Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level
- Item number
- 5.1.3A
- Analysis basis
- 1 cum
- Priced inputs
- 13
- Derived rate
- ₹8,404.05/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.1.3A (Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 4 graded stone aggregate 20 mm nominal size of Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 13 priced inputs for 1 cum and works out to ₹8,404.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal size | cum | 0.536 | 1,425.00 | 763.80 |
| 0279 | MAT | Recycled Concrete Aggregate (RCA) 20 mm nominal size | cum | 0.134 | 957.00 | 128.24 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal size | cum | 0.176 | 1,400.00 | 246.40 |
| 0281 | MAT | Recycled Concrete Aggregate (RCA) 10 mm nominal size | cum | 0.044 | 957.00 | 42.11 |
| 0982 | MAT | Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III) | cum | 0.36 | 1,450.00 | 516.20 |
| 0278 | MAT | Manufactured sand derived from Recycled Concrete Aggregate (RCA) | cum | 0.089 | 957.00 | 85.17 |
| 0367 | MAT | Portland Cement (0.2833cum)Portland Cement (OPC-43 Grade) | tonne | 0.32 | 5,156.00 | 1,649.92 |
| 0155 | LAB | Mason (average) | day | 0.17 | 857.00 | 145.69 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 0101 | LAB | Bhisti | day | 0.9 | 816.00 | 734.40 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.07 | 900.00 | 63.00 |
| 0012 | MACH | Vibrator (Needle type 40 mm) | day | 0.07 | 400.00 | 28.00 |
| 9999 | MAT | Sundries | L.S. | 14.3 | 2.27 | 32.46 |
- Total
- 5,907.39
- Add 1 % Water charges on “W”
- +59.07
- TOTAL
- 5,966.46
- Add GST on “X” (multiplying factor 0.2127)
- +1,269.07
- TOTAL
- 7,235.53
- Add 15% CPOH on “Y”
- +1,085.33
- TOTAL
- 8,320.86
- Add Cess @ 1% on “Z”
- +83.21
- Cost of 1 cum
- 8,404.07
- SAY
- ₹8,404.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 206
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 206. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate