Skip to main content
R/DAR 2023

Providing and fixing sheet covering over expansion joints with iron screws as per design Aluminium fluted strips 3.15 mm thick

200 mm wide
Item number
5.29.2.2
Analysis basis
1 metre
Priced inputs
6
Derived rate
₹753.85/ METRE
D-01/RATE ANALYSISITEM 5.29.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.29.2.2 (Providing and fixing sheet covering over expansion joints with iron screws as per design Aluminium fluted strips 3.15 mm thick 200 mm wide) is derived from 6 priced inputs for 1 metre and works out to ₹753.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 5.29.2.2DETAILS OF COST FOR 1 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2392MATStrips Aluminium fluted 3.15mm thick and 200mm wide metreStrips Aluminium fluted 3.15 mm thick and 200 mm widemetre1381.00381.00
0639MATBright finished or black enamelled mild steel screws 25 mmBright finished or black enameled mild steel screws 25 mmNos0.0642.002.52
9977MATCarriage of materialsL.S.1.32.272.95
0112LABCarpenter 2nd classday0.089816.0072.62
0114LABBeldarday0.089736.0065.50
9999MATSundriesL.S.2.342.275.31
BUILD-UP TO RATE
TOTAL
529.90
Add 1 % Water charges on “W”
+5.30
TOTAL
535.20
Add GST on “X” (multiplying factor 0.2127)
+113.84
TOTAL
649.04
Add 15% CPOH on “Y”
+97.36
TOTAL
746.40
Add Cess @ 1% on “Z”
+7.46
Cost for 1 metre
753.86
SAY
₹753.85
D-02/SOURCEPRINTED PAGE 271
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
271

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 271. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.