Providing and fixing sheet covering over expansion joints with iron screws as per design Aluminium fluted strips 3.15 mm thick
- Item number
- 5.29.2.1
- Analysis basis
- 1 metre
- Priced inputs
- 6
- Derived rate
- ₹567.60/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.29.2.1 (Providing and fixing sheet covering over expansion joints with iron screws as per design Aluminium fluted strips 3.15 mm thick 150 mm wide) is derived from 6 priced inputs for 1 metre and works out to ₹567.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2391 | MAT | Strips-Aluminium fluted 3.15mm thick and 150mm wideStrips-Aluminium fluted 3.15 mm thick and 150 mm wide | metre | 1 | 286.00 | 286.00 |
| 0639 | MAT | Bright finished or black enamelled mild steel screws 25 mmBright finished or black enameled mild steel screws 25 mm | Nos | 0.06 | 42.00 | 2.52 |
| 9977 | MAT | Carriage of materials | L.S. | 1.04 | 2.27 | 2.36 |
| 0112 | LAB | Carpenter 2nd class | day | 0.067 | 816.00 | 54.67 |
| 0114 | LAB | Beldar | day | 0.067 | 736.00 | 49.31 |
| 9999 | MAT | Sundries | L.S. | 1.82 | 2.27 | 4.13 |
- TOTAL
- 398.99
- Add 1 % Water charges on “W”
- +3.99
- TOTAL
- 402.98
- Add GST on “X” (multiplying factor 0.2127)
- +85.71
- TOTAL
- 488.69
- Add 15% CPOH on “Y”
- +73.30
- TOTAL
- 561.99
- Add Cess @ 1% on “Z”
- +5.62
- Cost for 1 metre
- 567.61
- SAY
- ₹567.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 271
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 271. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.