Providing and fixing sheet covering over expansion joints with iron screws as per design Non-asbestos 6 mm thick fibre cement board, Type-A, Category-III as per IS: 14862:2000
- Item number
- 5.29.1.2
- Analysis basis
- 3m length
- Priced inputs
- 5
- Derived rate
- ₹330.20/ M LENGTH
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.29.1.2 (Providing and fixing sheet covering over expansion joints with iron screws as per design Non-asbestos 6 mm thick fibre cement board, Type-A, Category-III as per IS: 14862:2000 200mm wide) is derived from 5 priced inputs for 3m length and works out to ₹330.20 per m length after water charges, GST, CPOH and cess. The full build-up is below.
- 0.46x0.63/0.47=0.62
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0251 | MAT | Non - Asbestos multi purpose fibre (high impact poly propelene reinforced) cement board 6mm thick Type-A, Category-III as per IS: 14862:2000 (3 x 0.20 = 0.60) + wastage @ 5% = 0.63 sqm6 mm thick fiber cement board Type A, Category III as per IS: 14862:2000 | sqm | 0.63 | 244.00 | 153.72 |
| 9999 | MAT | Transportation of fibre cement sheet and accessories upto site | L.S. | 0.62 | 2.27 | 1.41 |
| 9999 | MAT | 50mm iron screws with washer and rawl plugs | L.S. | 53.82 | 2.27 | 122.17 |
| 0112 | LAB | Carpenter 2nd class | day | 0.27 | 816.00 | 220.32 |
| 0114 | LAB | Beldar | day | 0.27 | 736.00 | 198.72 |
- TOTAL
- 696.34
- Add 1 % Water charges on “W”
- +6.96
- TOTAL
- 703.30
- Add GST on “X” (multiplying factor 0.2127)
- +149.59
- TOTAL
- 852.89
- Add 15% CPOH on “Y”
- +127.93
- TOTAL
- 980.82
- Add Cess @ 1% on “Z”
- +9.81
- Cost for 3 metre
- 990.63
- Cost per metre
- 330.21
- SAY
- ₹330.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 270
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 270. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate