Skip to main content
R/DAR 2023

Providing and fixing sheet covering over expansion joints with iron screws as per design Non-asbestos 6 mm thick fibre cement board, Type-A, Category-III as per IS: 14862:2000

200mm wide
Item number
5.29.1.2
Analysis basis
3m length
Priced inputs
5
Derived rate
₹330.20/ M LENGTH
D-01/RATE ANALYSISITEM 5.29.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.29.1.2 (Providing and fixing sheet covering over expansion joints with iron screws as per design Non-asbestos 6 mm thick fibre cement board, Type-A, Category-III as per IS: 14862:2000 200mm wide) is derived from 5 priced inputs for 3m length and works out to ₹330.20 per m length after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 0.46x0.63/0.47=0.62
ANALYSIS OF RATES · ITEM 5.29.1.2DETAILS OF COST FOR 3M LENGTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0251MATNon - Asbestos multi purpose fibre (high impact poly propelene reinforced) cement board 6mm thick Type-A, Category-III as per IS: 14862:2000 (3 x 0.20 = 0.60) + wastage @ 5% = 0.63 sqm6 mm thick fiber cement board Type A, Category III as per IS: 14862:2000sqm0.63244.00153.72
9999MATTransportation of fibre cement sheet and accessories upto siteL.S.0.622.271.41
9999MAT50mm iron screws with washer and rawl plugsL.S.53.822.27122.17
0112LABCarpenter 2nd classday0.27816.00220.32
0114LABBeldarday0.27736.00198.72
BUILD-UP TO RATE
TOTAL
696.34
Add 1 % Water charges on “W”
+6.96
TOTAL
703.30
Add GST on “X” (multiplying factor 0.2127)
+149.59
TOTAL
852.89
Add 15% CPOH on “Y”
+127.93
TOTAL
980.82
Add Cess @ 1% on “Z”
+9.81
Cost for 3 metre
990.63
Cost per metre
330.21
SAY
₹330.20
D-02/SOURCEPRINTED PAGE 270
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
270

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 270. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.