CPWD Analysis of Rates · Reinforced Cement Concrete

Providing and fixing sheet covering over expansion joints with iron screws as per design Non-asbestos 6 mm thick fibre cement board, Type-A, Category-III as per IS: 14862:2000

200mm wide

Item number
5.29.1.2
Analysis basis
Details of cost for 3m length
Priced inputs
5
Derived rate
330.20 / m length

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.29.1.2 Providing and fixing sheet covering over expansion joints with iron screws as per design Non-asbestos 6 mm thick fibre cement board, Type-A, Category-III as per IS: 14862:2000 200mm wide — is derived from 5 priced inputs for 3m length and works out to ₹330.20 per m length after water charges, GST, CPOH and cess. The full build-up is below.

  • 0.46x0.63/0.47=0.62
CodeInputUnitQuantityRate (INR)Amount (INR)
0251Non - Asbestos multi purpose fibre (high impact poly propelene reinforced) cement board 6mm thick Type-A, Category-III as per IS: 14862:2000 (3 x 0.20 = 0.60) + wastage @ 5% = 0.63 sqm6 mm thick fiber cement board Type A, Category III as per IS: 14862:2000Materialsqm0.63244.00153.72
9999Transportation of fibre cement sheet and accessories upto siteMaterialL.S.0.622.271.41
999950mm iron screws with washer and rawl plugsMaterialL.S.53.822.27122.17
0112Carpenter 2nd classLabourday0.27816.00220.32
0114BeldarLabourday0.27736.00198.72
TOTAL
696.34
Add 1 % Water charges on “W”
6.96
TOTAL
703.30
Add GST on “X” (multiplying factor 0.2127)
149.59
TOTAL
852.89
Add 15% CPOH on “Y”
127.93
TOTAL
980.82
Add Cess @ 1% on “Z”
9.81
Cost for 3 metre
990.63
Cost per metre
330.21
Say
330.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 270. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.