Skip to main content
R/DAR 2023

Providing and fixing sheet covering over expansion joints with iron screws as per design Cement bonded wood particle board 6mm thick as per IS : 14276

150 mm wide
Item number
5.29.3.1
Analysis basis
3 metre
Priced inputs
4
Derived rate
₹237.40/ METRE
D-01/RATE ANALYSISITEM 5.29.3.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.29.3.1 (Providing and fixing sheet covering over expansion joints with iron screws as per design Cement bonded wood particle board 6mm thick as per IS : 14276 150 mm wide) is derived from 4 priced inputs for 3 metre and works out to ₹237.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • LABOUR:
ANALYSIS OF RATES · ITEM 5.29.3.1DETAILS OF COST FOR 3 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0242MATMulti purpose cement bonded wood particle board 6 mm thick6 mm thick mulitipurpose cement bonded wood particle board conforming to IS : 14276sqm0.47210.0098.70
9999MAT50mm iron screws with washer and rawl plugsL.S40.32.2791.48
0112LABCarpenter 2nd classday0.2816.00163.20
0114LABBeldarday0.2736.00147.20
BUILD-UP TO RATE
TOTAL
500.58
Add 1 % Water charges on “W”
+5.01
TOTAL
505.59
Add GST on “X” (multiplying factor 0.2127)
+107.54
TOTAL
613.13
Add 15% CPOH on “Y”
+91.97
TOTAL
705.10
Add Cess @ 1% on “Z”
+7.05
Cost of 3 metre
712.15
Cost of 1 metre
237.38
SAY
₹237.40
D-02/SOURCEPRINTED PAGE 272
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
272

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 272. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.