CPWD Analysis of Rates · Reinforced Cement Concrete

Providing and fixing in position 12mm thick bitumen impregnated fiber board conforming to IS: 1838, including cost of primer, sealing compound Grade-A in expansion joints

Item number
5.28
Analysis basis
Details of cost for joint 100m long 10cm deep
Priced inputs
8
Derived rate
655.75 / joint 100m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.28 Providing and fixing in position 12mm thick bitumen impregnated fiber board conforming to IS: 1838, including cost of primer, sealing compound Grade-A in expansion joints — is derived from 8 priced inputs for joint 100m and works out to ₹655.75 per joint 100m after water charges, GST, CPOH and cess. The full build-up is below.

  • = 10 sqm
  • (i) Impregnated fibre board 1x100x0.075=7.5sqm
  • (ii) Primer 80m/litter 100m=100/80 x1=1.25 lit
  • (iii) Sealing compound @ 3 m per litre for
  • 100m = 100/3x1 =33.3 litres
  • Wastage @ 5% = 1.67
  • Total = 35.00 litre
  • (1 litre = 0.9 kg) = 35.00x0.9 = 31.5 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
0339Flame retardent face insulating, Impregnated fibre board 12 mm thickFlame retardant face insulating, Impregnated fibre board 12 mm thickMaterialsqm7.5412.003,090.00
0316Bitumen solution primer of approved qualityMateriallitre1.2550.0062.50
0314Bitumen hot sealing compound : grade AMaterialgram kilo-31.530.00945.00
9977CarriageMaterialL.S.26.912.2761.09
0123Mason 1st classMason 1st classLabourday0.12897.00107.64
0124Mason 2nd classMason 2nd classLabourday0.12816.0097.92
0114BeldarLabourday0.25736.00184.00
9999SundriesMaterialL.S.26.912.2761.09
TOTAL
4,609.24
Add 1 % Water charges on “W”
46.09
TOTAL
4,655.33
Add GST on “X” (multiplying factor 0.2127)
990.19
TOTAL
5,645.52
Add 15% CPOH on “Y”
846.83
TOTAL
6,492.35
Add Cess @ 1% on “Z”
64.92
Cost for 100m long 10cm deep
6,557.27
Cost per cm depth per 100m long
655.73
Say
655.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 269. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.