Providing and fixing in position 12mm thick bitumen impregnated fiber board conforming to IS: 1838, including cost of primer, sealing compound Grade-A in expansion joints

Item number
5.28
Analysis basis
joint 100m
Priced inputs
8
Derived rate
₹655.75/ JOINT 100M
D-01/RATE ANALYSISITEM 5.28

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.28 (Providing and fixing in position 12mm thick bitumen impregnated fiber board conforming to IS: 1838, including cost of primer, sealing compound Grade-A in expansion joints) is derived from 8 priced inputs for joint 100m and works out to ₹655.75 per joint 100m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • = 10 sqm
  • (i) Impregnated fibre board 1x100x0.075=7.5sqm
  • (ii) Primer 80m/litter 100m=100/80 x1=1.25 lit
  • (iii) Sealing compound @ 3 m per litre for
  • 100m = 100/3x1 =33.3 litres
  • Wastage @ 5% = 1.67
  • Total = 35.00 litre
  • (1 litre = 0.9 kg) = 35.00x0.9 = 31.5 kg
ANALYSIS OF RATES · ITEM 5.28DETAILS OF COST FOR JOINT 100M LONG 10CM DEEP
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0339MATFlame retardent face insulating, Impregnated fibre board 12 mm thickFlame retardant face insulating, Impregnated fibre board 12 mm thicksqm7.5412.003,090.00
0316MATBitumen solution primer of approved qualitylitre1.2550.0062.50
0314MATBitumen hot sealing compound : grade Agram kilo-31.530.00945.00
9977MATCarriageL.S.26.912.2761.09
0123LABMason 1st classMason 1st classday0.12897.00107.64
0124LABMason 2nd classMason 2nd classday0.12816.0097.92
0114LABBeldarday0.25736.00184.00
9999MATSundriesL.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
4,609.24
Add 1 % Water charges on “W”
+46.09
TOTAL
4,655.33
Add GST on “X” (multiplying factor 0.2127)
+990.19
TOTAL
5,645.52
Add 15% CPOH on “Y”
+846.83
TOTAL
6,492.35
Add Cess @ 1% on “Z”
+64.92
Cost for 100m long 10cm deep
6,557.27
Cost per cm depth per 100m long
655.73
SAY
₹655.75
D-02/SOURCEPRINTED PAGE 269
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
269

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 269. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE