CPWD Analysis of Rates · Reinforced Cement Concrete
Providing and fixing in position 12mm thick bitumen impregnated fiber board conforming to IS: 1838, including cost of primer, sealing compound Grade-A in expansion joints
- Item number
- 5.28
- Analysis basis
- Details of cost for joint 100m long 10cm deep
- Priced inputs
- 8
- Derived rate
- ₹655.75 / joint 100m
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.28 — Providing and fixing in position 12mm thick bitumen impregnated fiber board conforming to IS: 1838, including cost of primer, sealing compound Grade-A in expansion joints — is derived from 8 priced inputs for joint 100m and works out to ₹655.75 per joint 100m after water charges, GST, CPOH and cess. The full build-up is below.
- = 10 sqm
- (i) Impregnated fibre board 1x100x0.075=7.5sqm
- (ii) Primer 80m/litter 100m=100/80 x1=1.25 lit
- (iii) Sealing compound @ 3 m per litre for
- 100m = 100/3x1 =33.3 litres
- Wastage @ 5% = 1.67
- Total = 35.00 litre
- (1 litre = 0.9 kg) = 35.00x0.9 = 31.5 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0339 | Flame retardent face insulating, Impregnated fibre board 12 mm thickFlame retardant face insulating, Impregnated fibre board 12 mm thickMaterial | sqm | 7.5 | 412.00 | 3,090.00 |
| 0316 | Bitumen solution primer of approved qualityMaterial | litre | 1.25 | 50.00 | 62.50 |
| 0314 | Bitumen hot sealing compound : grade AMaterial | gram kilo- | 31.5 | 30.00 | 945.00 |
| 9977 | CarriageMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.12 | 897.00 | 107.64 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.12 | 816.00 | 97.92 |
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 9999 | SundriesMaterial | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 4,609.24
- Add 1 % Water charges on “W”
- 46.09
- TOTAL
- 4,655.33
- Add GST on “X” (multiplying factor 0.2127)
- 990.19
- TOTAL
- 5,645.52
- Add 15% CPOH on “Y”
- 846.83
- TOTAL
- 6,492.35
- Add Cess @ 1% on “Z”
- 64.92
- Cost for 100m long 10cm deep
- 6,557.27
- Cost per cm depth per 100m long
- 655.73
- Say
- 655.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 269. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.