Smooth finishing of the exposed surface of R.C.C. work with 6 mm thick cement mortar 1:3 (1 Cement : 3 fine sand)

Item number
5.23
Analysis basis
Details of cost for 10sqm.
Priced inputs
6
Derived rate
₹300.45
D-01/RATE ANALYSISITEM 5.23

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.23 (Smooth finishing of the exposed surface of R.C.C. work with 6 mm thick cement mortar 1:3 (1 Cement : 3 fine sand)) is derived from 6 priced inputs and works out to ₹300.45 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 3 (1 cement : 3 fine sand)
ANALYSIS OF RATES · ITEM 5.23DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No 3.3 of SH: MortarsRate as per item 3.3cum0.0724,379.05315.29
0155LABMason (average)day0.51857.00437.07
0115LABCoolieday0.75736.00552.00
0101LABBhistiday0.92816.00750.72
9999MATExtra for removing burrs, cleaning with wire brushes pock marking with pointed tool etc. completeL.S.13.392.2730.40
9999MATScaffolding and SundriesL.S.11.72.2726.56
BUILD-UP TO RATE
TOTAL
2,112.04
Add 1 % Water charges on “W”
+21.12
TOTAL
2,133.16
Add GST on “X” (multiplying factor 0.2127)
+453.72
TOTAL
2,586.88
Add 15% CPOH on “Y”
+388.03
TOTAL
2,974.91
Add Cess @ 1% on “Z”
+29.75
Cost of 10 Sqm.
3,004.66
Cost per sqm.
300.47
SAY
₹300.45
D-02/SOURCEPRINTED PAGE 266
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
266

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 266. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.