CPWD Analysis of Rates · Reinforced Cement Concrete
Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from
factory/workshop to construction site including placing in position and binding all complete above plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more
- Item number
- 5.22C.1
- Analysis basis
- Details of cost for 1 quintal-
- Priced inputs
- 6
- Derived rate
- ₹99.65 / Kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.22C.1 — Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from factory/workshop to construction site including placing in position and binding all complete above plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more — is derived from 6 priced inputs for 1 quintal and works out to ₹99.65 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Deformed twisted steel bars = 1.00 q
- For binding and placing in position
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1005 | Twisted steel / deformed barsTwisted steel/ deformed TMT bars Fe-500DMaterial | quintal | 1 | 5,550.00 | 5,550.00 |
| 9999 | Cover blockMaterial | L.S. | 26 | 2.27 | 59.02 |
| 9999 | For cut and bendMaterial | L.S. | 156 | 2.27 | 354.12 |
| 0102 | Blacksmith 1st classLabour | day | 0.6 | 897.00 | 538.20 |
| 0114 | BeldarLabour | day | 0.6 | 736.00 | 441.60 |
| 9999 | Sundries and binding wireMaterial | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 7,004.03
- Add 1 % Water charges
- 70.04
- TOTAL
- 7,074.07
- Add GST on “X” (multiplying factor 0.2127)
- 1,504.65
- TOTAL
- 8,578.72
- Add 15% CPOH on “Y”
- 1,286.81
- TOTAL
- 9,865.53
- Add Cess @1% on “Z”
- 98.66
- Cost of one quintal
- 9,964.19
- Cost of 1 Kg.
- 99.64
- Say
- 99.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 266. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.