Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from factory/workshop to construction site including placing in position and binding all complete upto plinth level

Thermo-Mechanically Treated bars of grade Fe-500D or more

Item number
5.22B.1
Analysis basis
Details of cost for 1 quintal-
Priced inputs
6
Derived rate
99.65 / Kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.22B.1 Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from factory/workshop to construction site including placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more — is derived from 6 priced inputs for 1 quintal and works out to ₹99.65 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • Deformed twisted steel bars = 1.00 q
  • For binding and placing in position
CodeInputUnitQuantityRate (INR)Amount (INR)
1005Twisted steel / deformed barsTwisted steel/ deformed TMT bars Fe-500DMaterialquintal15,550.005,550.00
9999Cover blockMaterialL.S.262.2759.02
9999For cut and bendMaterialL.S.1562.27354.12
0102Blacksmith 1st classLabourday0.6897.00538.20
0114BeldarLabourday0.6736.00441.60
9999Sundries and binding wireMaterialL.S.26.912.2761.09
TOTAL
7,004.03
Add 1 % Water charges
70.04
TOTAL
7,074.07
Add GST on “X” (multiplying factor 0.2127)
1,504.65
TOTAL
8,578.72
Add 15% CPOH on “Y”
1,286.81
TOTAL
9,865.53
Add Cess @1% on “Z”
98.66
Cost of one quintal
9,964.19
Cost of 1 Kg.
99.64
Say
99.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 265. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works