Extra for rendering smooth the top of suspended floors, landings and staircases (treads and risers) with cement mortar 1:2 (1 cement : 2 coarse sand), including a floating coat of neat cement and protecting the surface with a layer of 7.5 cm of earth laid over 15 mm of fine sand in case of suspended floor and bricks laid in mud mortar in case of landings and steps, including subsequent removal and cleaning of the same
- Item number
- 5.24
- Analysis basis
- Details of cost for 100sqm.
- Priced inputs
- 9
- Derived rate
- ₹150.50
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.24 (Extra for rendering smooth the top of suspended floors, landings and staircases (treads and risers) with cement mortar 1:2 (1 cement : 2 coarse sand), including a floating coat of neat cement and protecting the surface with a layer of 7.5 cm of earth laid over 15 mm of fine sand in case of suspended floor and bricks laid in mud mortar in case of landings and steps, including subsequent removal and cleaning of the same) is derived from 9 priced inputs and works out to ₹150.50 after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:2 (1 Cement :2 Coarse
- sand)
- Spreading sand 15mm thick on floor
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item No 3.7 of SH: MortarsRate as per item 3.7 | cum | 0.3 | 5,584.50 | 1,675.35 | |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.213 | 5,156.00 | 1,098.23 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 2 | 897.00 | 1,794.00 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 2 | 816.00 | 1,632.00 |
| 0114 | LAB | Beldar | day | 2.5 | 736.00 | 1,840.00 |
| 9999 | MAT | Spreading earth on floor (7.5mm thick) | L.S. | 354.9 | 2.27 | 805.62 |
| 0983 | MAT | Fine sand (zone IV) | cum | 1.5 | 980.00 | 1,470.00 |
| 9999 | MAT | Disposal of earth spread over floor protectIron | L.S. | 53.3 | 2.27 | 120.99 |
| 9999 | MAT | Sundries | L.S. | 62.4 | 2.27 | 141.65 |
- TOTAL
- 10,577.84
- Add 1 % Water charges on “W”
- +105.78
- TOTAL
- 10,683.62
- Add GST on “X” (multiplying factor 0.2127)
- +2,272.41
- TOTAL
- 12,956.03
- Add 15% CPOH on “Y”
- +1,943.40
- TOTAL
- 14,899.43
- Add Cess @ 1% on “Z”
- +148.99
- Cost of 100 Sqm.
- 15,048.42
- Cost per sqm.
- 150.48
- SAY
- ₹150.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 267
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 267. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.