CPWD Analysis of Rates · Reinforced Cement Concrete

Extra for rendering smooth the top of suspended floors, landings and staircases (treads and risers) with cement mortar 1:2 (1 cement : 2 coarse sand), including a floating coat of neat cement and protecting the surface with a layer of 7.5 cm of earth laid over 15 mm of fine sand in case of suspended floor and bricks laid in mud mortar in case of landings and steps, including subsequent removal and cleaning of the same

Item number
5.24
Analysis basis
Details of cost for 100sqm.
Priced inputs
9
Derived rate
150.50

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.24 Extra for rendering smooth the top of suspended floors, landings and staircases (treads and risers) with cement mortar 1:2 (1 cement : 2 coarse sand), including a floating coat of neat cement and protecting the surface with a layer of 7.5 cm of earth laid over 15 mm of fine sand in case of suspended floor and bricks laid in mud mortar in case of landings and steps, including subsequent removal and cleaning of the same — is derived from 9 priced inputs and works out to ₹150.50 after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1:2 (1 Cement :2 Coarse
  • sand)
  • Spreading sand 15mm thick on floor
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item No 3.7 of SH: MortarsRate as per item 3.7Sub-analysiscum0.35,584.501,675.35
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.2135,156.001,098.23
0123Mason 1st classMason 1st classLabourday2897.001,794.00
0124Mason 2nd classMason 2nd classLabourday2816.001,632.00
0114BeldarLabourday2.5736.001,840.00
9999Spreading earth on floor (7.5mm thick)MaterialL.S.354.92.27805.62
0983Fine sand (zone IV)Materialcum1.5980.001,470.00
9999Disposal of earth spread over floor protectIronMaterialL.S.53.32.27120.99
9999SundriesMaterialL.S.62.42.27141.65
TOTAL
10,577.84
Add 1 % Water charges on “W”
105.78
TOTAL
10,683.62
Add GST on “X” (multiplying factor 0.2127)
2,272.41
TOTAL
12,956.03
Add 15% CPOH on “Y”
1,943.40
TOTAL
14,899.43
Add Cess @ 1% on “Z”
148.99
Cost of 100 Sqm.
15,048.42
Cost per sqm.
150.48
Say
150.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 267. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works