CPWD Analysis of Rates · Reinforced Cement Concrete

Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) including centering and shuttering complete but excluding cost of reinforcement

Item number
5.19A
Analysis basis
Details of cost for 0.424 cum
Priced inputs
8
Derived rate
15,918.60 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.19A Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) including centering and shuttering complete but excluding cost of reinforcement — is derived from 8 priced inputs for 0.424 cum and works out to ₹15,918.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider 2 R.S. Joists (150mmx80mm)
  • 4.88m long placed 30cm apart centre to
  • centre
  • Overall dimensions of the beam 43cmx20cm
  • MATERIAL:
  • Concrete work :4.93x0.43x0.20 = 0.424 cum
  • For 1:1.5:3 Cement Concrete (1 cement:
  • 1 coarse sand (RCA) upto 20% : 3 stone
  • aggregate 20mm nominal size (RCA) upto
  • 20½%)
  • Extra labour for laying C.C. in RCC work
  • Form work-4.93x0.83 girth = 4.09 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1Sub-analysiscum0.4248,170.053,464.10
0114BeldarLabourday0.042736.0030.91
0101BhistiLabourday0.085816.0069.36
0123Mason 1st classMason 1st classLabourday0.017897.0015.25
0124Mason 2nd classMason 2nd classLabourday0.017816.0013.87
0128MateLabourday0.017816.0013.87
Rate as per Item Number 5.9.5 of SH: Reinforced cement concrete workRate as per item 5.9.5Sub-analysissqm4.09736.403,011.88
9999Sundries and for lifting materialsMaterialL.S.21.582.2748.99
Total
6,668.23
Add 1 % Water charges on “W-A”
1.92
TOTAL
6,670.15
Add GST on “X-A” (multiplying factor 0.2127)
41.30
TOTAL
6,711.45
Add 15% CPOH on “Y-A”
35.32
TOTAL
6,746.77
Add Cess @ 1% on “Z-A”
2.71
Cost of 0.424 cum
6,749.48
Cost of 1 cum
15,918.58
Say
15,918.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 256. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.