CPWD Analysis of Rates · Reinforced Cement Concrete
Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) including centering and shuttering complete but excluding cost of reinforcement
- Item number
- 5.19A
- Analysis basis
- Details of cost for 0.424 cum
- Priced inputs
- 8
- Derived rate
- ₹15,918.60 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.19A — Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) including centering and shuttering complete but excluding cost of reinforcement — is derived from 8 priced inputs for 0.424 cum and works out to ₹15,918.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Consider 2 R.S. Joists (150mmx80mm)
- 4.88m long placed 30cm apart centre to
- centre
- Overall dimensions of the beam 43cmx20cm
- MATERIAL:
- Concrete work :4.93x0.43x0.20 = 0.424 cum
- For 1:1.5:3 Cement Concrete (1 cement:
- 1 coarse sand (RCA) upto 20% : 3 stone
- aggregate 20mm nominal size (RCA) upto
- 20½%)
- Extra labour for laying C.C. in RCC work
- Form work-4.93x0.83 girth = 4.09 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1Sub-analysis | cum | 0.424 | 8,170.05 | 3,464.10 | |
| 0114 | BeldarLabour | day | 0.042 | 736.00 | 30.91 |
| 0101 | BhistiLabour | day | 0.085 | 816.00 | 69.36 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.017 | 897.00 | 15.25 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.017 | 816.00 | 13.87 |
| 0128 | MateLabour | day | 0.017 | 816.00 | 13.87 |
| Rate as per Item Number 5.9.5 of SH: Reinforced cement concrete workRate as per item 5.9.5Sub-analysis | sqm | 4.09 | 736.40 | 3,011.88 | |
| 9999 | Sundries and for lifting materialsMaterial | L.S. | 21.58 | 2.27 | 48.99 |
- Total
- 6,668.23
- Add 1 % Water charges on “W-A”
- 1.92
- TOTAL
- 6,670.15
- Add GST on “X-A” (multiplying factor 0.2127)
- 41.30
- TOTAL
- 6,711.45
- Add 15% CPOH on “Y-A”
- 35.32
- TOTAL
- 6,746.77
- Add Cess @ 1% on “Z-A”
- 2.71
- Cost of 0.424 cum
- 6,749.48
- Cost of 1 cum
- 15,918.58
- Say
- 15,918.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 256. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.