Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) including centering and shuttering complete but , excluding cost of reinforcement

Item number
5.19
Analysis basis
Details of cost for 0.424 cum.
Priced inputs
8
Derived rate
16,089.40 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.19 Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) including centering and shuttering complete but , excluding cost of reinforcement — is derived from 8 priced inputs for 0.424 cum and works out to ₹16,089.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Consider 2 R.S. Joist (150mmx80mm) 4.88m
  • long placed 30cm apart centre to centre
  • Overall dimensions of the beam 43cmx20cmConcrete work- 4.93x0.43x0.20 = 0.424 cum
  • for 1:1 :3 Cement Concrete (1 cement: 1
  • coarse sand : 3 stone aggregate 20mm
  • nomina½l size) ½
  • Extra labour for laying C.C. in RCC work
  • Form work4.93x0.83 girth = 4.09 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4.1.2 of SH: Concrete WorkRate as per item 4.1.2Sub-analysiscum0.4248,340.853,536.52
0114BeldarLabourday0.042736.0030.91
0101BhistiLabourday0.085816.0069.36
0123Mason 1st classMason 1st classLabourday0.017897.0015.25
0124Mason 2nd classMason 2nd classLabourday0.017816.0013.87
0128MateLabourday0.017816.0013.87
Rate as per item 5.9.5 of SH: Reinforced cement concrete workRate as per item 5.9.5Sub-analysissqm4.09736.403,011.88
9999Sundries and for lifting materialsMaterialL.S.21.582.2748.99
TOTAL
6,740.65
Add 1 % Water charges on “W-A”
1.92
TOTAL
6,742.57
Add GST on “X-A” (multiplying factor 0.2127)
41.30
TOTAL
6,783.87
Add 15% CPOH on “Y-A”
35.32
TOTAL
6,819.19
Add Cess @ 1% on “Z-A”
2.71
Cost of 0.424 cum
6,821.90
Cost of 1 cum.
16,089.39
Say
16,089.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 255. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate