Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) including centering and shuttering complete but , excluding cost of reinforcement
- Item number
- 5.19
- Analysis basis
- 0.424 cum
- Priced inputs
- 8
- Derived rate
- ₹16,089.40/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.19 (Encasing rolled steel sections, in beams and columns, with cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) including centering and shuttering complete but , excluding cost of reinforcement) is derived from 8 priced inputs for 0.424 cum and works out to ₹16,089.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Consider 2 R.S. Joist (150mmx80mm) 4.88m
- long placed 30cm apart centre to centre
- Overall dimensions of the beam 43cmx20cmConcrete work- 4.93x0.43x0.20 = 0.424 cum
- for 1:1 :3 Cement Concrete (1 cement: 1
- coarse sand : 3 stone aggregate 20mm
- nomina½l size) ½
- Extra labour for laying C.C. in RCC work
- Form work4.93x0.83 girth = 4.09 sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.4.1.2 of SH: Concrete WorkRate as per item 4.1.2 | cum | 0.424 | 8,340.85 | 3,536.52 | |
| 0114 | LAB | Beldar | day | 0.042 | 736.00 | 30.91 |
| 0101 | LAB | Bhisti | day | 0.085 | 816.00 | 69.36 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.017 | 897.00 | 15.25 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.017 | 816.00 | 13.87 |
| 0128 | LAB | Mate | day | 0.017 | 816.00 | 13.87 |
| SUB | Rate as per item 5.9.5 of SH: Reinforced cement concrete workRate as per item 5.9.5 | sqm | 4.09 | 736.40 | 3,011.88 | |
| 9999 | MAT | Sundries and for lifting materials | L.S. | 21.58 | 2.27 | 48.99 |
- TOTAL
- 6,740.65
- Add 1 % Water charges on “W-A”
- +1.92
- TOTAL
- 6,742.57
- Add GST on “X-A” (multiplying factor 0.2127)
- +41.30
- TOTAL
- 6,783.87
- Add 15% CPOH on “Y-A”
- +35.32
- TOTAL
- 6,819.19
- Add Cess @ 1% on “Z-A”
- +2.71
- Cost of 0.424 cum
- 6,821.90
- Cost of 1 cum.
- 16,089.39
- SAY
- ₹16,089.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 255
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 255. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.