CPWD Analysis of Rates · Reinforced Cement Concrete

Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits

25 mm thick

Item number
5.18.3
Analysis basis
Details of cost for jali 0.75mx0.5m = 0.375 sqm
Priced inputs
6
Derived rate
1,539.00 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.18.3 Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits 25 mm thick — is derived from 6 priced inputs for jali 0 and works out to ₹1,539.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0770Cement Concrete Jali 25 mm thickMaterialsqm0.375295.00110.63
9999Mortar for fixingMaterialL.S.1.822.274.13
9988Carriage and sundriesMaterialL.S.1.822.274.13
0123Mason 1st classMason 1st classLabourday0.06897.0053.82
0124Mason 2nd classMason 2nd classLabourday0.06816.0048.96
0114BeldarLabourday0.25736.00184.00
TOTAL
405.67
Add 1 % Water charges on “W”
4.06
TOTAL
409.73
Add GST on “X” (multiplying factor 0.2127)
87.15
TOTAL
496.88
Add 15% CPOH on “Y”
74.53
TOTAL
571.41
Add Cess @ 1% on “Z”
5.71
Cost of 0.375 sqm.
577.12
Cost of 1 sqm.
1,538.99
Say
1,539.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 255. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.