Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits
- Item number
- 5.18.2
- Analysis basis
- Details of cost for 1.2mx0.60m = 0.72 sqm.
- Priced inputs
- 6
- Derived rate
- ₹1,706.55/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.18.2 (Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits 40 mm thick) is derived from 6 priced inputs and works out to ₹1,706.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0769 | MAT | Cement Concrete Jali 40 mm thick | sqm | 0.72 | 380.00 | 273.60 |
| 9999 | MAT | Mortar for fixing | L.S. | 3.64 | 2.27 | 8.26 |
| 9988 | MAT | Carriage and sundries | L.S. | 3.64 | 2.27 | 8.26 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.12 | 897.00 | 107.64 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.12 | 816.00 | 97.92 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
- TOTAL
- 863.68
- Add 1 % Water charges on “W”
- +8.64
- TOTAL
- 872.32
- Add GST on “X” (multiplying factor 0.2127)
- +185.54
- TOTAL
- 1,057.86
- Add 15% CPOH on “Y”
- +158.68
- TOTAL
- 1,216.54
- Add Cess @ 1% on “Z”
- +12.17
- Cost of 0.72 sqm.
- 1,228.71
- Cost of 1 sqm.
- 1,706.54
- SAY
- ₹1,706.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 254
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 254. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate