Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits

40 mm thick
Item number
5.18.2
Analysis basis
Details of cost for 1.2mx0.60m = 0.72 sqm.
Priced inputs
6
Derived rate
₹1,706.55/ SQM
D-01/RATE ANALYSISITEM 5.18.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.18.2 (Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits 40 mm thick) is derived from 6 priced inputs and works out to ₹1,706.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 5.18.2DETAILS OF COST FOR 1.2MX0.60M = 0.72 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0769MATCement Concrete Jali 40 mm thicksqm0.72380.00273.60
9999MATMortar for fixingL.S.3.642.278.26
9988MATCarriage and sundriesL.S.3.642.278.26
0123LABMason 1st classMason 1st classday0.12897.00107.64
0124LABMason 2nd classMason 2nd classday0.12816.0097.92
0114LABBeldarday0.5736.00368.00
BUILD-UP TO RATE
TOTAL
863.68
Add 1 % Water charges on “W”
+8.64
TOTAL
872.32
Add GST on “X” (multiplying factor 0.2127)
+185.54
TOTAL
1,057.86
Add 15% CPOH on “Y”
+158.68
TOTAL
1,216.54
Add Cess @ 1% on “Z”
+12.17
Cost of 0.72 sqm.
1,228.71
Cost of 1 sqm.
1,706.54
SAY
₹1,706.55
D-02/SOURCEPRINTED PAGE 254
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
254

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 254. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.