CPWD Analysis of Rates · Reinforced Cement Concrete
Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits
50 mm thick
- Item number
- 5.18.1
- Analysis basis
- Details of cost for jali 2.00mx0.75m = 1.50
- Priced inputs
- 6
- Derived rate
- ₹1,886.90 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.18.1 — Providing precast cement concrete Jali 1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 6mm nominal size ), reinforced with 1.6 mm dia mild steel wire, including centering and shuttering, roughening cleaning, fixing and finishing in cement mortar 1:3 (1 cement: 3 fine sand) etc. complete, excluding plastering of the jambs, sills and soffits 50 mm thick — is derived from 6 priced inputs for jali 2 and works out to ₹1,886.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0768 | Cement Concrete Jali 50 mm thickMaterial | sqm | 1.5 | 435.00 | 652.50 |
| 9999 | Mortar for fixingMaterial | L.S. | 6.24 | 2.27 | 14.16 |
| 9988 | Carriage and sundriesMaterial | L.S. | 6.2 | 2.27 | 14.07 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.3 | 897.00 | 269.10 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.3 | 816.00 | 244.80 |
| 0114 | BeldarLabour | day | 1.08 | 736.00 | 794.88 |
- TOTAL
- 1,989.51
- Add 1 % Water charges on “W”
- 19.90
- TOTAL
- 2,009.41
- Add GST on “X” (multiplying factor 0.2127)
- 427.40
- TOTAL
- 2,436.81
- Add 15% CPOH on “Y”
- 365.52
- TOTAL
- 2,802.33
- Add Cess @ 1% on “Z”
- 28.02
- Cost of 1.50 sqm.
- 2,830.35
- Cost of 1 sqm.
- 1,886.90
- Say
- 1,886.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 254. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.