Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in vertical & horizontal fins individually or forming box louvers setting in cement mortar 1:2 (1 cement : 2 coarse sand), including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.17A
Analysis basis
10 Nos
Priced inputs
11
Derived rate
₹11,872.55/ CUM
D-01/RATE ANALYSISITEM 5.17A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.17A (Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in vertical & horizontal fins individually or forming box louvers setting in cement mortar 1:2 (1 cement : 2 coarse sand), including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 11 priced inputs for 10 Nos and works out to ₹11,872.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • fins 4m high at lm centre to centre with two
  • horizontal fins, all projecting 60cm from face
  • of wall and 5cm thick cubical contents = 10x
  • 0.66 cum = 6.6 cum
  • MATERIAL:
  • Cement concrete 1:1.5:3
  • Centering and shuttering
  • Extra labour for lifting from FL II upto Floor
  • Level V (Coolie =
  • 6.6x0.75x1.50=7.4)
  • LABOUR:
  • Extra labour for laying cement concrete in
  • RCC work due to delay etc.
ANALYSIS OF RATES · ITEM 5.17ADETAILS OF COST FOR 10 NOS. OF 4 RCC VERTICAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1cum6.68,170.0553,922.33
SUBRate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1sqm25.6392.1510,039.04
0115LABCoolieday7.4736.005,446.40
0114LABBeldarday0.66736.00485.76
0101LABBhistiday1.32816.001,077.12
0123LABMason 1st classMason 1st classday0.264897.00236.81
0124LABMason 2nd classMason 2nd classday0.264816.00215.42
0128LABMateday0.264816.00215.42
9999MATCement mortar 1:3 for fixingL.S.179.42.27407.24
9999MATLabour for hoisting, Transporting and settingL.S.717.62.271,628.95
9999MATSundriesL.S.179.42.27407.24
BUILD-UP TO RATE
Total
74,081.73
Add 1 % Water charges on “W-A”
+101.20
TOTAL
74,182.93
Add GST on “X-A” (multiplying factor 0.2127)
+2,174.13
TOTAL
76,357.06
Add 15% CPOH on “Y-A”
+1,859.35
TOTAL
78,216.41
Add Cess @ 1% on “Z-A”
+142.55
Cost of 6.6 cum
78,358.96
Cost of 1 cum
11,872.57
SAY
₹11,872.55
D-02/SOURCEPRINTED PAGE 253
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
253

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 253. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.