Skip to main content

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in vertical & horizontal fins, individually or forming box louvers, setting in cement mortar 1:2 (1 cement : 2 coarse sand), including the cost of required centering, shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.17
Analysis basis
10 Nos
Priced inputs
11
Derived rate
₹12,043.35/ NOS
D-01/RATE ANALYSISITEM 5.17

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.17 (Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in vertical & horizontal fins, individually or forming box louvers, setting in cement mortar 1:2 (1 cement : 2 coarse sand), including the cost of required centering, shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 11 priced inputs for 10 Nos and works out to ₹12,043.35 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • fins 4m high at 1m centre to centre with two
  • horizontal fins, all projecting 60cm from face
  • of wall and 5cm thick cubical contents = 10x
  • 0.66 cum = 6.6 cum
  • Cement concrete 1:1 :3
  • Centering and shuttering
  • Extra labour for lifting from FL II upto Floor
  • Level V (Coolie
  • =6.6x0.75x1.50=7.4)
  • Extra labour for laying cement concrete in
  • RCC work due to delay etc.
ANALYSIS OF RATES · ITEM 5.17DETAILS OF COST FOR 10 NOS. OF 4 RCC VERTICAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2cum6.68,340.8555,049.61
SUBRate as per item no. 4.3.1 of SH: Concrete workRate as per item 4.3.1sqm25.6392.1510,039.04
0115LABCoolieday7.4736.005,446.40
0114LABBeldarday0.66736.00485.76
0101LABBhistiday1.32816.001,077.12
0123LABMason 1st classMason 1st classday0.264897.00236.81
0124LABMason 2nd classMason 2nd classday0.264816.00215.42
0128LABMateday0.264816.00215.42
9999MATCement mortar 1:3 for fixingL.S.179.42.27407.24
9999MATLabour for hoisting, Transporting and setting in positionL.S.717.62.271,628.95
9999MATSundriesL.S.179.42.27407.24
BUILD-UP TO RATE
TOTAL
75,209.01
Add 1 % Water charges on “W-A”
+101.20
TOTAL
75,310.21
Add GST on “X-A” (multiplying factor 0.2127)
+2,174.13
TOTAL
77,484.34
Add 15% CPOH on “Y-A”
+1,859.35
TOTAL
79,343.69
Add Cess @ 1% on “Z-A”
+142.55
Cost for 6.6 cum
79,486.24
Cost for 1 cum.
12,043.37
SAY
₹12,043.35
D-02/SOURCEPRINTED PAGE 252
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
252

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 252. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.