Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.16A
Analysis basis
Details of cost for 10 shelf 0.90x0.45x0.04m
Priced inputs
11
Derived rate
20,185.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.16A Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 11 priced inputs for 10 shelf and works out to ₹20,185.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • thick = 10x0.90x0.45x0.04m = 0.162 cum
  • Cement concrete 1:1.5:3
  • Finisihing
  • Centring and shuttering = 10x2x(0.90+0.45)
  • x0.04 = 1.08 sqm
  • Extra labour for lifting from FL II upto Floor
  • Level V (Coolie
  • =0.162x0.75x1.50=0.18)
  • LABOUR:
  • Extra labour for laying cement concrete in
  • RCC work due to delay etc.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1Sub-analysiscum0.1628,170.051,323.55
Rate as per Item Number 13.18 of SH: FinishingRate as per item 13.18Sub-analysissqm8.579.95679.58
Rate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1Sub-analysissqm1.08392.15423.52
0115CoolieLabourday0.18736.00132.48
0114BeldarLabourday0.016736.0011.78
0101BhistiLabourday0.032816.0026.11
0123Mason 1st classMason 1st classLabourday0.006897.005.38
0124Mason 2nd classMason 2nd classLabourday0.006816.004.90
0128MateLabourday0.006816.004.90
9999Cement mortar 1:3 for fixingMaterialL.S.44.22.27100.33
9999Labour for hoisting, Transporting and settingMaterialL.S.135.22.27306.90
Total
3,019.43
Add 1 % Water charges on “W-A”
5.93
TOTAL
3,025.36
Add GST on “X-A” (multiplying factor 0.2127)
127.35
TOTAL
3,152.71
Add 15% CPOH on “Y-A”
108.91
TOTAL
3,261.62
Add Cess @ 1% on “Z-A”
8.35
Cost of 0.162 cum
3,269.97
Cost of 1 cum
20,185.00
Say
20,185.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 251. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works