Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.16A
Analysis basis
10 shelf
Priced inputs
11
Derived rate
₹20,185.00/ CUM
D-01/RATE ANALYSISITEM 5.16A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.16A (Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 11 priced inputs for 10 shelf and works out to ₹20,185.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • thick = 10x0.90x0.45x0.04m = 0.162 cum
  • Cement concrete 1:1.5:3
  • Finisihing
  • Centring and shuttering = 10x2x(0.90+0.45)
  • x0.04 = 1.08 sqm
  • Extra labour for lifting from FL II upto Floor
  • Level V (Coolie
  • =0.162x0.75x1.50=0.18)
  • LABOUR:
  • Extra labour for laying cement concrete in
  • RCC work due to delay etc.
ANALYSIS OF RATES · ITEM 5.16ADETAILS OF COST FOR 10 SHELF 0.90X0.45X0.04M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1cum0.1628,170.051,323.55
SUBRate as per Item Number 13.18 of SH: FinishingRate as per item 13.18sqm8.579.95679.58
SUBRate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1sqm1.08392.15423.52
0115LABCoolieday0.18736.00132.48
0114LABBeldarday0.016736.0011.78
0101LABBhistiday0.032816.0026.11
0123LABMason 1st classMason 1st classday0.006897.005.38
0124LABMason 2nd classMason 2nd classday0.006816.004.90
0128LABMateday0.006816.004.90
9999MATCement mortar 1:3 for fixingL.S.44.22.27100.33
9999MATLabour for hoisting, Transporting and settingL.S.135.22.27306.90
BUILD-UP TO RATE
Total
3,019.43
Add 1 % Water charges on “W-A”
+5.93
TOTAL
3,025.36
Add GST on “X-A” (multiplying factor 0.2127)
+127.35
TOTAL
3,152.71
Add 15% CPOH on “Y-A”
+108.91
TOTAL
3,261.62
Add Cess @ 1% on “Z-A”
+8.35
Cost of 0.162 cum
3,269.97
Cost of 1 cum
20,185.00
SAY
₹20,185.00
D-02/SOURCEPRINTED PAGE 251
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
251

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 251. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.