Skip to main content

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves, including setting in cement mortar 1:3 (1cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.16
Analysis basis
10 Nos
Priced inputs
11
Derived rate
₹20,355.80/ NOS
D-01/RATE ANALYSISITEM 5.16

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.16 (Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in shelves, including setting in cement mortar 1:3 (1cement : 3 coarse sand), cost of required centering, shuttering and finishing with neat cement punning on exposed surfaces but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 11 priced inputs for 10 Nos and works out to ₹20,355.80 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • shelf 0.90x0.45x0.04m thick =
  • 10x0.90x0.45x0.04m = 0.162 cum
  • Cement concrete 1:1 :3
  • Finishing
  • Centring and shuttering:
  • Centring and shuttering = 10x2x(0.90+0.45)
  • x0.04 = 1.08 sqm
  • Extra labour for lifting from FL II upto Floor
  • Level V (Coolie
  • =0.162x0.75x1.50=0.18)
  • Extra labour for laying cement concrete in
  • RCC work due to delay etc.
ANALYSIS OF RATES · ITEM 5.16DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2cum0.1628,340.851,351.22
SUBRate same as per iem no. 13.18 of SH : FinishingRate as per item 13.18sqm8.579.95679.58
SUBRate same as per item no. 4.3.1 of SH : concrete workRate as per item 4.3.1sqm1.08392.15423.52
0115LABCoolieday0.18736.00132.48
0114LABBeldarday0.016736.0011.78
0101LABBhistiday0.032816.0026.11
0123LABMason 1st classMason 1st classday0.006897.005.38
0124LABMason 2nd classMason 2nd classday0.006816.004.90
0128LABMateday0.006816.004.90
9999MATCement mortar 1:3 for fixingL.S.44.22.27100.33
9999MATLabour for hoisting, Transporting and setting in positionL.S.135.22.27306.90
BUILD-UP TO RATE
TOTAL
3,047.10
Add 1 % Water charges on “W-A”
+5.93
TOTAL
3,053.03
Add GST on “X-A” (multiplying factor 0.2127)
+127.35
TOTAL
3,180.38
Add 15% CPOH on “Y-A”
+108.91
TOTAL
3,289.29
Add Cess @ 1% on “Z-A”
+8.35
Cost for 0.162 cum
3,297.64
Cost for 1 cum.
20,355.80
SAY
₹20,355.80
D-02/SOURCEPRINTED PAGE 250
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
250

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 250. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.