CPWD Analysis of Rates · Reinforced Cement Concrete

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but excluding the cost of reinforcement with, 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.15A
Analysis basis
Details of cost for 10 Nos. beam 6.60m
Priced inputs
10
Derived rate
13,728.40 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.15A Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but excluding the cost of reinforcement with, 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 10 priced inputs for 10 Nos and works out to ₹13,728.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • long 0.50m deep and 0.30m wide =
  • 10x6.60x0.50x0.30 = 9.9 cum
  • MATERIAL:
  • Cement concrete 1:1.5:3
  • Centring and shuttering
  • Extra labour for lifting above
  • FL II upto Floor Level V
  • (Coolie =9.9x0.75x1.50=11.1)
  • LABOUR:
  • Extra labour for laying cement concrete in
  • RCCwork
  • 0.10x9.9
  • 0.20x9.9
  • 0.04x9.9
  • 0.04x9.9
  • 0.04x9.9
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1Sub-analysiscum9.98,170.0580,883.50
Rate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1Sub-analysissqm69392.1527,058.35
0115CoolieLabourday11.1736.008,169.60
0114BeldarLabourday0.99736.00728.64
0101BhistiLabourday1.98816.001,615.68
0123Mason 1st classMason 1st classLabourday0.396897.00355.21
0124Mason 2nd classMason 2nd classLabourday0.396816.00323.14
0128MateLabourday0.396816.00323.14
9999Cement mortar 1:3 for fixingMaterialL.S.8972.272,036.19
9999Labour for hoisting, Transporting and setting in positionMaterialL.S.2,6912.276,108.57
Total
1,27,602.02
Add 1 % Water charges on “W-A”
196.60
TOTAL
1,27,798.62
Add GST on “X-A” (multiplying factor 0.2127)
4,223.53
TOTAL
1,32,022.15
Add 15% CPOH on “Y-A”
3,612.05
TOTAL
1,35,634.20
Add Cess @ 1% on “Z-A”
276.92
Cost of 9.9 cum
1,35,911.12
Cost of 1 cum
13,728.40
Say
13,728.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 249. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.