Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but excluding the cost of reinforcement with, 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.15A
Analysis basis
10 Nos
Priced inputs
10
Derived rate
₹13,728.40/ CUM
D-01/RATE ANALYSISITEM 5.15A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.15A (Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but excluding the cost of reinforcement with, 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 10 priced inputs for 10 Nos and works out to ₹13,728.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • long 0.50m deep and 0.30m wide =
  • 10x6.60x0.50x0.30 = 9.9 cum
  • MATERIAL:
  • Cement concrete 1:1.5:3
  • Centring and shuttering
  • Extra labour for lifting above
  • FL II upto Floor Level V
  • (Coolie =9.9x0.75x1.50=11.1)
  • LABOUR:
  • Extra labour for laying cement concrete in
  • RCCwork
  • 0.10x9.9
  • 0.20x9.9
  • 0.04x9.9
  • 0.04x9.9
  • 0.04x9.9
ANALYSIS OF RATES · ITEM 5.15ADETAILS OF COST FOR 10 NOS. BEAM 6.60M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1cum9.98,170.0580,883.50
SUBRate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1sqm69392.1527,058.35
0115LABCoolieday11.1736.008,169.60
0114LABBeldarday0.99736.00728.64
0101LABBhistiday1.98816.001,615.68
0123LABMason 1st classMason 1st classday0.396897.00355.21
0124LABMason 2nd classMason 2nd classday0.396816.00323.14
0128LABMateday0.396816.00323.14
9999MATCement mortar 1:3 for fixingL.S.8972.272,036.19
9999MATLabour for hoisting, Transporting and setting in positionL.S.2,6912.276,108.57
BUILD-UP TO RATE
Total
1,27,602.02
Add 1 % Water charges on “W-A”
+196.60
TOTAL
1,27,798.62
Add GST on “X-A” (multiplying factor 0.2127)
+4,223.53
TOTAL
1,32,022.15
Add 15% CPOH on “Y-A”
+3,612.05
TOTAL
1,35,634.20
Add Cess @ 1% on “Z-A”
+276.92
Cost of 9.9 cum
1,35,911.12
Cost of 1 cum
13,728.40
SAY
₹13,728.40
D-02/SOURCEPRINTED PAGE 249
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
249

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 249. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.