Skip to main content

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers, including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.15
Analysis basis
Details of cost for10 Nos. beam 6.60m
Priced inputs
10
Derived rate
₹13,899.20
D-01/RATE ANALYSISITEM 5.15

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.15 (Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers, including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 10 priced inputs and works out to ₹13,899.20 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • long 0.50m deep and 0.30m wide =
  • 10x6.60x0.50x0.30 = 9.9 cum.
  • Cement concrete 1:1 :3
  • Centring and shuttering
  • Extra labour for lifting above
  • FL II upto Floor Level V
  • (Coolie =9.9x0.75x1.50=11.1)
  • Extra labour for laying cement concrete in
  • RCC work
  • 0.10x9.9
  • 0.20x9.9
  • 0.04x9.9
  • 0.04x9.9
  • 0.04x9.9
ANALYSIS OF RATES · ITEM 5.15DETAILS OF COST FOR10 NOS. BEAM 6.60M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2cum9.98,340.8582,574.42
SUBRate same as per item no. 4.3.1 of SH: Concrete workRate as per item 4.3.1sqm69392.1527,058.35
0115LABCoolieday11.1736.008,169.60
0114LABBeldarday0.99736.00728.64
0101LABBhistiday1.98816.001,615.68
0123LABMason 1st classMason 1st classday0.396897.00355.21
0124LABMason 2nd classMason 2nd classday0.396816.00323.14
0128LABMateday0.396816.00323.14
9999MATCement mortar 1:3 for fixingL.S.8972.272,036.19
9999MATLabour for hoisting, Transporting and setting in positionL.S.2,6912.276,108.57
BUILD-UP TO RATE
TOTAL
1,29,292.94
Add 1 % Water charges on “W-A”
+196.60
TOTAL
1,29,489.54
Add GST on “X-A” (multiplying factor 0.2127)
+4,223.53
TOTAL
1,33,713.07
Add 15% CPOH on “Y-A”
+3,612.05
TOTAL
1,37,325.12
Add Cess @ 1% on “Z-A”
+276.92
Cost for 9.9 cum
1,37,602.04
Cost for 1 cum.
13,899.20
SAY
₹13,899.20
D-02/SOURCEPRINTED PAGE 248
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
248

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 248. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.