CPWD Analysis of Rates · Reinforced Cement Concrete

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers, including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.15
Analysis basis
Details of cost for10 Nos. beam 6.60m
Priced inputs
10
Derived rate
13,899.20

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.15 Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in lintels, beams and bressumers, including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost of required centering and shuttering but , excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 10 priced inputs and works out to ₹13,899.20 after water charges, GST, CPOH and cess. The full build-up is below.

  • long 0.50m deep and 0.30m wide =
  • 10x6.60x0.50x0.30 = 9.9 cum.
  • Cement concrete 1:1 :3
  • Centring and shuttering
  • Extra labour for lifting above
  • FL II upto Floor Level V
  • (Coolie =9.9x0.75x1.50=11.1)
  • Extra labour for laying cement concrete in
  • RCC work
  • 0.10x9.9
  • 0.20x9.9
  • 0.04x9.9
  • 0.04x9.9
  • 0.04x9.9
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2Sub-analysiscum9.98,340.8582,574.42
Rate same as per item no. 4.3.1 of SH: Concrete workRate as per item 4.3.1Sub-analysissqm69392.1527,058.35
0115CoolieLabourday11.1736.008,169.60
0114BeldarLabourday0.99736.00728.64
0101BhistiLabourday1.98816.001,615.68
0123Mason 1st classMason 1st classLabourday0.396897.00355.21
0124Mason 2nd classMason 2nd classLabourday0.396816.00323.14
0128MateLabourday0.396816.00323.14
9999Cement mortar 1:3 for fixingMaterialL.S.8972.272,036.19
9999Labour for hoisting, Transporting and setting in positionMaterialL.S.2,6912.276,108.57
TOTAL
1,29,292.94
Add 1 % Water charges on “W-A”
196.60
TOTAL
1,29,489.54
Add GST on “X-A” (multiplying factor 0.2127)
4,223.53
TOTAL
1,33,713.07
Add 15% CPOH on “Y-A”
3,612.05
TOTAL
1,37,325.12
Add Cess @ 1% on “Z-A”
276.92
Cost for 9.9 cum
1,37,602.04
Cost for 1 cum.
13,899.20
Say
13,899.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 248. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.