CPWD Analysis of Rates · Reinforced Cement Concrete
Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc. including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
- Item number
- 5.14A
- Analysis basis
- Details of cost for 10x 1 x 0.20 x 0.15 = 0.3
- Priced inputs
- 14
- Derived rate
- ₹18,064.15 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.14A — Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc. including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 14 priced inputs for 10x 1 and works out to ₹18,064.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- cum
- MATERIAL:
- Cement concrete 1:1.5:3
- Extra labour for lifting above FL II upto FL V
- 0.3 x 1.5x0.75 = 0.34
- Centring and shuttering
- 53.82x0.3 = 16.1
- LABOUR:
- 0.58x0.3=0.174
- 0.58x0.3=0.174
- 1.5x0.3=0.450
- 0.06x0.3=0.018
- Extra labour for laying CC in RCC
- 0.1x0.3=0.030
- 0.2x0.3=0.060
- 0.04x0.3=0.012
- 0.04x0.3=0.012
- 0.04x0.3=0.012
- Add Extra labour for moulding
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1Sub-analysis | cum | 0.3 | 8,170.05 | 2,451.02 | |
| 0115 | CoolieLabour | day | 0.34 | 736.00 | 250.24 |
| 9999 | Mortar and labour for hoisting and for fixingMaterial | L.S. | 27.3 | 2.27 | 61.97 |
| Rate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1Sub-analysis | sqm | 3.6 | 392.15 | 1,411.74 | |
| 9999 | Add for extra labour for hoistingMaterial | L.S. | 16.1 | 2.27 | 36.55 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.174 | 897.00 | 156.08 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.174 | 816.00 | 141.98 |
| 0115 | CoolieLabour | day | 0.45 | 736.00 | 331.20 |
| 0101 | BhistiLabour | day | 0.018 | 816.00 | 14.69 |
| 0114 | BeldarLabour | day | 0.03 | 736.00 | 22.08 |
| 0101 | BhistiLabour | day | 0.06 | 816.00 | 48.96 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.012 | 897.00 | 10.76 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.012 | 816.00 | 9.79 |
| 0128 | MateLabour | day | 0.012 | 816.00 | 9.79 |
- Total
- 4,956.85
- Add 1 % Water charges on “W-A”
- 10.94
- TOTAL
- 4,967.79
- Add GST on “X-A” (multiplying factor 0.2127)
- 235.04
- TOTAL
- 5,202.83
- Add 15% CPOH on “Y-A”
- 201.01
- TOTAL
- 5,403.84
- Add Cess @ 1% on “Z-A”
- 15.41
- Cost of 0.3 cum
- 5,419.25
- Cost of 1 cum
- 18,064.17
- Say
- 18,064.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 247. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.