Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc. including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.14A
Analysis basis
Details of cost for 10x 1 x 0.20 x 0.15 = 0.3
Priced inputs
14
Derived rate
18,064.15 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.14A Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc. including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 14 priced inputs for 10x 1 and works out to ₹18,064.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • cum
  • MATERIAL:
  • Cement concrete 1:1.5:3
  • Extra labour for lifting above FL II upto FL V
  • 0.3 x 1.5x0.75 = 0.34
  • Centring and shuttering
  • 53.82x0.3 = 16.1
  • LABOUR:
  • 0.58x0.3=0.174
  • 0.58x0.3=0.174
  • 1.5x0.3=0.450
  • 0.06x0.3=0.018
  • Extra labour for laying CC in RCC
  • 0.1x0.3=0.030
  • 0.2x0.3=0.060
  • 0.04x0.3=0.012
  • 0.04x0.3=0.012
  • 0.04x0.3=0.012
  • Add Extra labour for moulding
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1Sub-analysiscum0.38,170.052,451.02
0115CoolieLabourday0.34736.00250.24
9999Mortar and labour for hoisting and for fixingMaterialL.S.27.32.2761.97
Rate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1Sub-analysissqm3.6392.151,411.74
9999Add for extra labour for hoistingMaterialL.S.16.12.2736.55
0123Mason 1st classMason 1st classLabourday0.174897.00156.08
0124Mason 2nd classMason 2nd classLabourday0.174816.00141.98
0115CoolieLabourday0.45736.00331.20
0101BhistiLabourday0.018816.0014.69
0114BeldarLabourday0.03736.0022.08
0101BhistiLabourday0.06816.0048.96
0123Mason 1st classMason 1st classLabourday0.012897.0010.76
0124Mason 2nd classMason 2nd classLabourday0.012816.009.79
0128MateLabourday0.012816.009.79
Total
4,956.85
Add 1 % Water charges on “W-A”
10.94
TOTAL
4,967.79
Add GST on “X-A” (multiplying factor 0.2127)
235.04
TOTAL
5,202.83
Add 15% CPOH on “Y-A”
201.01
TOTAL
5,403.84
Add Cess @ 1% on “Z-A”
15.41
Cost of 0.3 cum
5,419.25
Cost of 1 cum
18,064.17
Say
18,064.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 247. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works