Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.14
Analysis basis
Details of cost for 10x1mx0.20x0.15=0.3 cum
Priced inputs
14
Derived rate
₹18,234.95
D-01/RATE ANALYSISITEM 5.14

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.14 (Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 14 priced inputs and works out to ₹18,234.95 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:1 :3
  • Extra labour for lifting above FL II upto FL V
  • 0.3 x 1.5x0.75 = 0.34
  • Centring and shuttering
  • 53.82x0.3 = 16.1
  • 0.58x0.3=0.174
  • 0.58x0.3=0.174
  • 1.5x0.3=0.450
  • 0.06x0.3=0.018
  • Extra labour for laying CC in RCC
  • 0.1x0.3=0.030
  • 0.2x0.3=0.060
  • 0.04x0.3=0.012
  • 0.04x0.3=0.012
  • 0.04x0.3=0.012
  • Add Extra labour for moulding :
ANALYSIS OF RATES · ITEM 5.14DETAILS OF COST FOR 10X1MX0.20X0.15=0.3 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2cum0.38,340.852,502.26
0115LABCoolieday0.34736.00250.24
9999MATMortar and labour for hoisting and for fixingL.S.27.32.2761.97
SUBRate as per Item No.4.3.1 of SH: Concrete WorkRate as per item 4.3.1sqm3.6392.151,411.74
9999MATAdd for extra labour for hoistingL.S.16.12.2736.55
0123LABMason 1st classMason 1st classday0.174897.00156.08
0124LABMason 2nd classMason 2nd classday0.174816.00141.98
0115LABCoolieday0.45736.00331.20
0101LABBhistiday0.018816.0014.69
0114LABBeldarday0.03736.0022.08
0101LABBhistiday0.06816.0048.96
0123LABMason 1st classMason 1st classday0.012897.0010.76
0124LABMason 2nd classMason 2nd classday0.012816.009.79
0128LABMateday0.012816.009.79
BUILD-UP TO RATE
TOTAL
5,008.09
Add 1 % Water charges on “W-A”
+10.94
TOTAL
5,019.03
Add GST on “X-A” (multiplying factor 0.2127)
+235.04
TOTAL
5,254.07
Add 15% CPOH on “Y-A”
+201.01
TOTAL
5,455.08
Add Cess @ 1% on “Z-A”
+15.41
Cost for 0.3 cum
5,470.49
Cost for 1 cum.
18,234.97
SAY
₹18,234.95
D-02/SOURCEPRINTED PAGE 246
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
246

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 246. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.