CPWD Analysis of Rates · Reinforced Cement Concrete
Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
- Item number
- 5.14
- Analysis basis
- Details of cost for 10x1mx0.20x0.15=0.3 cum
- Priced inputs
- 14
- Derived rate
- ₹18,234.95
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.14 — Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 14 priced inputs and works out to ₹18,234.95 after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:1 :3
- Extra labour for lifting above FL II upto FL V
- 0.3 x 1.5x0.75 = 0.34
- Centring and shuttering
- 53.82x0.3 = 16.1
- 0.58x0.3=0.174
- 0.58x0.3=0.174
- 1.5x0.3=0.450
- 0.06x0.3=0.018
- Extra labour for laying CC in RCC
- 0.1x0.3=0.030
- 0.2x0.3=0.060
- 0.04x0.3=0.012
- 0.04x0.3=0.012
- 0.04x0.3=0.012
- Add Extra labour for moulding :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2Sub-analysis | cum | 0.3 | 8,340.85 | 2,502.26 | |
| 0115 | CoolieLabour | day | 0.34 | 736.00 | 250.24 |
| 9999 | Mortar and labour for hoisting and for fixingMaterial | L.S. | 27.3 | 2.27 | 61.97 |
| Rate as per Item No.4.3.1 of SH: Concrete WorkRate as per item 4.3.1Sub-analysis | sqm | 3.6 | 392.15 | 1,411.74 | |
| 9999 | Add for extra labour for hoistingMaterial | L.S. | 16.1 | 2.27 | 36.55 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.174 | 897.00 | 156.08 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.174 | 816.00 | 141.98 |
| 0115 | CoolieLabour | day | 0.45 | 736.00 | 331.20 |
| 0101 | BhistiLabour | day | 0.018 | 816.00 | 14.69 |
| 0114 | BeldarLabour | day | 0.03 | 736.00 | 22.08 |
| 0101 | BhistiLabour | day | 0.06 | 816.00 | 48.96 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.012 | 897.00 | 10.76 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.012 | 816.00 | 9.79 |
| 0128 | MateLabour | day | 0.012 | 816.00 | 9.79 |
- TOTAL
- 5,008.09
- Add 1 % Water charges on “W-A”
- 10.94
- TOTAL
- 5,019.03
- Add GST on “X-A” (multiplying factor 0.2127)
- 235.04
- TOTAL
- 5,254.07
- Add 15% CPOH on “Y-A”
- 201.01
- TOTAL
- 5,455.08
- Add Cess @ 1% on “Z-A”
- 15.41
- Cost for 0.3 cum
- 5,470.49
- Cost for 1 cum.
- 18,234.97
- Say
- 18,234.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 246. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works