Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.14
Analysis basis
Details of cost for 10x1mx0.20x0.15=0.3 cum
Priced inputs
14
Derived rate
18,234.95

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.14 Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in mouldings as in cornices, windows sills etc, including setting in cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centering, shuttering but, excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 14 priced inputs and works out to ₹18,234.95 after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:1 :3
  • Extra labour for lifting above FL II upto FL V
  • 0.3 x 1.5x0.75 = 0.34
  • Centring and shuttering
  • 53.82x0.3 = 16.1
  • 0.58x0.3=0.174
  • 0.58x0.3=0.174
  • 1.5x0.3=0.450
  • 0.06x0.3=0.018
  • Extra labour for laying CC in RCC
  • 0.1x0.3=0.030
  • 0.2x0.3=0.060
  • 0.04x0.3=0.012
  • 0.04x0.3=0.012
  • 0.04x0.3=0.012
  • Add Extra labour for moulding :
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2Sub-analysiscum0.38,340.852,502.26
0115CoolieLabourday0.34736.00250.24
9999Mortar and labour for hoisting and for fixingMaterialL.S.27.32.2761.97
Rate as per Item No.4.3.1 of SH: Concrete WorkRate as per item 4.3.1Sub-analysissqm3.6392.151,411.74
9999Add for extra labour for hoistingMaterialL.S.16.12.2736.55
0123Mason 1st classMason 1st classLabourday0.174897.00156.08
0124Mason 2nd classMason 2nd classLabourday0.174816.00141.98
0115CoolieLabourday0.45736.00331.20
0101BhistiLabourday0.018816.0014.69
0114BeldarLabourday0.03736.0022.08
0101BhistiLabourday0.06816.0048.96
0123Mason 1st classMason 1st classLabourday0.012897.0010.76
0124Mason 2nd classMason 2nd classLabourday0.012816.009.79
0128MateLabourday0.012816.009.79
TOTAL
5,008.09
Add 1 % Water charges on “W-A”
10.94
TOTAL
5,019.03
Add GST on “X-A” (multiplying factor 0.2127)
235.04
TOTAL
5,254.07
Add 15% CPOH on “Y-A”
201.01
TOTAL
5,455.08
Add Cess @ 1% on “Z-A”
15.41
Cost for 0.3 cum
5,470.49
Cost for 1 cum.
18,234.97
Say
18,234.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 246. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.