1:1.5:3 (1 cement : 1.5 coarse sand Including (Based Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including on item Recycled Concrete Aggregate (RCA) upto 20%). no. 4.1.2)

Item number
5.13A/Sub-AR-4
Analysis basis
1 cum
Priced inputs
14
Derived rate
₹9,353.20/ CUM
D-01/RATE ANALYSISITEM 5.13A/Sub-AR-4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.13A/Sub-AR-4 (1:1.5:3 (1 cement : 1.5 coarse sand Including (Based Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including on item Recycled Concrete Aggregate (RCA) upto 20%). no. 4.1.2)) is derived from 14 priced inputs for 1 cum and works out to ₹9,353.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • (Extra labour for lifting material above FLII
  • upto floor V level = 0.75 x 1.50 = 1.13 for
  • precast concrete)
ANALYSIS OF RATES · ITEM 5.13A/Sub-AR-4DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal sizecum0.4561,425.00649.80
0279MATRecycled Concrete Aggregate (RCA) 20 mm nominal sizecum0.114957.00109.10
0297MATStone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal sizecum0.2241,400.00313.60
0281MATRecycled Concrete Aggregate (RCA) 10 mm nominal sizecum0.056957.0053.59
0982MATCoarse sand (zone III) derived from natural sourcesCoarse sand (zone III)cum0.341,450.00493.00
0278MATManufactured sand derived from Recycled Concrete Aggregate (RCA)cum0.085957.0081.35
0367MATPortland Cement (0.2833cum)Portland Cement (OPC-43 Grade)tonne0.45,156.002,062.40
0155LABMason (average)day0.1857.0085.70
0114LABBeldarday1.63736.001,199.68
0101LABBhistiday0.7816.00571.20
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.07900.0063.00
0012MACHVibrator (Needle type 40 mm)day0.07400.0028.00
9999MATSundriesL.S.14.32.2732.46
0115LABCoolieday1.13736.00831.68
BUILD-UP TO RATE
Total
6,574.56
Add 1 % Water charges on “W”
+65.75
TOTAL
6,640.31
Add GST on “X” (multiplying factor 0.2127)
+1,412.39
TOTAL
8,052.70
Add 15% CPOH on “Y”
+1,207.91
TOTAL
9,260.61
Add Cess @ 1% on “Z”
+92.61
Cost of 1 cum
9,353.22
SAY
₹9,353.20
D-02/SOURCEPRINTED PAGE 245
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
245

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 245. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.