CPWD Analysis of Rates · Reinforced Cement Concrete

1:1.5:3 (1 cement : 1.5 coarse sand Including (Based Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including on item Recycled Concrete Aggregate (RCA) upto 20%). no. 4.1.2)

Item number
5.13A/Sub-AR-4
Analysis basis
Details of cost for 1 cum
Priced inputs
14
Derived rate
9,353.20 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.13A/Sub-AR-4 1:1.5:3 (1 cement : 1.5 coarse sand Including (Based Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including on item Recycled Concrete Aggregate (RCA) upto 20%). no. 4.1.2) — is derived from 14 priced inputs for 1 cum and works out to ₹9,353.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • (Extra labour for lifting material above FLII
  • upto floor V level = 0.75 x 1.50 = 1.13 for
  • precast concrete)
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.4561,425.00649.80
0279Recycled Concrete Aggregate (RCA) 20 mm nominal sizeMaterialcum0.114957.00109.10
0297Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.2241,400.00313.60
0281Recycled Concrete Aggregate (RCA) 10 mm nominal sizeMaterialcum0.056957.0053.59
0982Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III)Materialcum0.341,450.00493.00
0278Manufactured sand derived from Recycled Concrete Aggregate (RCA)Materialcum0.085957.0081.35
0367Portland Cement (0.2833cum)Portland Cement (OPC-43 Grade)Materialtonne0.45,156.002,062.40
0155Mason (average)Labourday0.1857.0085.70
0114BeldarLabourday1.63736.001,199.68
0101BhistiLabourday0.7816.00571.20
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.07900.0063.00
0012Vibrator (Needle type 40 mm)Machineryday0.07400.0028.00
9999SundriesMaterialL.S.14.32.2732.46
0115CoolieLabourday1.13736.00831.68
Total
6,574.56
Add 1 % Water charges on “W”
65.75
TOTAL
6,640.31
Add GST on “X” (multiplying factor 0.2127)
1,412.39
TOTAL
8,052.70
Add 15% CPOH on “Y”
1,207.91
TOTAL
9,260.61
Add Cess @ 1% on “Z”
92.61
Cost of 1 cum
9,353.22
Say
9,353.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 245. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.