1:1.5:3 (1 cement : 1.5 coarse sand Including (Based Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including on item Recycled Concrete Aggregate (RCA) upto 20%). no. 4.1.2)
- Item number
- 5.13A/Sub-AR-4
- Analysis basis
- 1 cum
- Priced inputs
- 14
- Derived rate
- ₹9,353.20/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.13A/Sub-AR-4 (1:1.5:3 (1 cement : 1.5 coarse sand Including (Based Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including on item Recycled Concrete Aggregate (RCA) upto 20%). no. 4.1.2)) is derived from 14 priced inputs for 1 cum and works out to ₹9,353.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- (Extra labour for lifting material above FLII
- upto floor V level = 0.75 x 1.50 = 1.13 for
- precast concrete)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 20 mm nominal size | cum | 0.456 | 1,425.00 | 649.80 |
| 0279 | MAT | Recycled Concrete Aggregate (RCA) 20 mm nominal size | cum | 0.114 | 957.00 | 109.10 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size derived from natural sourcesStone Aggregate (Single size) : 10 mm nominal size | cum | 0.224 | 1,400.00 | 313.60 |
| 0281 | MAT | Recycled Concrete Aggregate (RCA) 10 mm nominal size | cum | 0.056 | 957.00 | 53.59 |
| 0982 | MAT | Coarse sand (zone III) derived from natural sourcesCoarse sand (zone III) | cum | 0.34 | 1,450.00 | 493.00 |
| 0278 | MAT | Manufactured sand derived from Recycled Concrete Aggregate (RCA) | cum | 0.085 | 957.00 | 81.35 |
| 0367 | MAT | Portland Cement (0.2833cum)Portland Cement (OPC-43 Grade) | tonne | 0.4 | 5,156.00 | 2,062.40 |
| 0155 | LAB | Mason (average) | day | 0.1 | 857.00 | 85.70 |
| 0114 | LAB | Beldar | day | 1.63 | 736.00 | 1,199.68 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.07 | 900.00 | 63.00 |
| 0012 | MACH | Vibrator (Needle type 40 mm) | day | 0.07 | 400.00 | 28.00 |
| 9999 | MAT | Sundries | L.S. | 14.3 | 2.27 | 32.46 |
| 0115 | LAB | Coolie | day | 1.13 | 736.00 | 831.68 |
- Total
- 6,574.56
- Add 1 % Water charges on “W”
- +65.75
- TOTAL
- 6,640.31
- Add GST on “X” (multiplying factor 0.2127)
- +1,412.39
- TOTAL
- 8,052.70
- Add 15% CPOH on “Y”
- +1,207.91
- TOTAL
- 9,260.61
- Add Cess @ 1% on “Z”
- +92.61
- Cost of 1 cum
- 9,353.22
- SAY
- ₹9,353.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 245
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 245. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.