CPWD Analysis of Rates · Reinforced Cement Concrete
Providing, hoisting and fixing up to floor five level precast reinforced cement concrete in small lintels not exceeding 1.5 m clear span up to floor five level, including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
- Item number
- 5.13A
- Analysis basis
- Details of cost for a lintel Qty = 0.054 cum
- Priced inputs
- 7
- Derived rate
- ₹14,155.35 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.13A — Providing, hoisting and fixing up to floor five level precast reinforced cement concrete in small lintels not exceeding 1.5 m clear span up to floor five level, including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 7 priced inputs for a lintel and works out to ₹14,155.35 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- 1.5m clear span = 1.8x0.20x0.15 = 0.054
- cum.
- Cement Concrete 1:1.5:3
- Centring and shuttering
- Extra labour for laying CC in RCC work
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Sub AR-4Rate as per item Sub AR-4Sub-analysis | cum | 0.054 | 9,353.20 | 505.07 | |
| Rate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1Sub-analysis | sqm | 0.6 | 392.15 | 235.29 | |
| 0114 | BeldarLabour | day | 0.005 | 736.00 | 3.68 |
| 0101 | BhistiLabour | day | 0.01 | 816.00 | 8.16 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0 | 897.00 | 1.79 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0 | 816.00 | 1.63 |
| 0128 | MateLabour | day | 0 | 816.00 | 1.63 |
- Total
- 757.25
- Add 1 % Water charges on “W-A”
- 0.17
- TOTAL
- 757.42
- Add GST on “X-A” (multiplying factor 0.2127)
- 3.63
- TOTAL
- 761.05
- Add 15% CPOH on “Y-A”
- 3.10
- TOTAL
- 764.15
- Add Cess @ 1% on “Z-A”
- 0.24
- Cost of 0.054 cum
- 764.39
- Cost of 1 cum
- 14,155.37
- Say
- 14,155.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 245. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works