Providing, hoisting and fixing up to floor five level precast reinforced cement concrete in small lintels not exceeding 1.5 m clear span up to floor five level, including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
- Item number
- 5.13A
- Analysis basis
- a lintel
- Priced inputs
- 7
- Derived rate
- ₹14,155.35/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.13A (Providing, hoisting and fixing up to floor five level precast reinforced cement concrete in small lintels not exceeding 1.5 m clear span up to floor five level, including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 7 priced inputs for a lintel and works out to ₹14,155.35 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- 1.5m clear span = 1.8x0.20x0.15 = 0.054
- cum.
- Cement Concrete 1:1.5:3
- Centring and shuttering
- Extra labour for laying CC in RCC work
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Sub AR-4Rate as per item Sub AR-4 | cum | 0.054 | 9,353.20 | 505.07 | |
| SUB | Rate as per Item Number 4.3.1 of SH: Concrete workRate as per item 4.3.1 | sqm | 0.6 | 392.15 | 235.29 | |
| 0114 | LAB | Beldar | day | 0.005 | 736.00 | 3.68 |
| 0101 | LAB | Bhisti | day | 0.01 | 816.00 | 8.16 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0 | 897.00 | 1.79 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0 | 816.00 | 1.63 |
| 0128 | LAB | Mate | day | 0 | 816.00 | 1.63 |
- Total
- 757.25
- Add 1 % Water charges on “W-A”
- +0.17
- TOTAL
- 757.42
- Add GST on “X-A” (multiplying factor 0.2127)
- +3.63
- TOTAL
- 761.05
- Add 15% CPOH on “Y-A”
- +3.10
- TOTAL
- 764.15
- Add Cess @ 1% on “Z-A”
- +0.24
- Cost of 0.054 cum
- 764.39
- Cost of 1 cum
- 14,155.37
- SAY
- ₹14,155.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 245
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 245. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.