Providing, hoisting and fixing up to floor five level precast reinforced cement concrete in small lintels not exceeding 1.5m clear span up to floor five level, including the cost of required centering, shuttering but , excluding the cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
- Item number
- 5.13
- Analysis basis
- a lintel
- Priced inputs
- 8
- Derived rate
- ₹14,325.95/ A LINTEL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.13 (Providing, hoisting and fixing up to floor five level precast reinforced cement concrete in small lintels not exceeding 1.5m clear span up to floor five level, including the cost of required centering, shuttering but , excluding the cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 8 priced inputs for a lintel and works out to ₹14,325.95 per a lintel after water charges, GST, CPOH and cess. The full build-up is below.
- Qty = 0.054 cum
- 1.5m clear span = 1.8x0.20x0.15 = 0.054
- cum.
- Cement Concrete 1:1 :3
- Extra labour for lifting material above FLII
- upto floor V level =0.054x 0.75 x 1.50 =
- 0.061 ( for precast concrete)
- Centring and shuttering
- Extra labour for laying CC in RCC work
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.4.1.2 of SH: Concrete Work ½Rate as per item 4.1.2 | cum | 0.054 | 8,340.85 | 450.41 | |
| 0115 | LAB | Coolie | day | 0.061 | 736.00 | 44.90 |
| SUB | Rate as per item no. 4.3.1 of SH: Concrete workRate as per item 4.3.1 | sqm | 0.6 | 392.15 | 235.29 | |
| 0114 | LAB | Beldar | day | 0.005 | 736.00 | 3.68 |
| 0101 | LAB | Bhisti | day | 0.01 | 816.00 | 8.16 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.002 | 897.00 | 1.79 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.002 | 816.00 | 1.63 |
| 0128 | LAB | Mate | day | 0.002 | 816.00 | 1.63 |
- TOTAL
- 747.49
- Add 1 % Water charges on “W-A”
- +0.62
- TOTAL
- 748.11
- Add GST on “X-A” (multiplying factor 0.2127)
- +13.27
- TOTAL
- 761.38
- Add 15% CPOH on “Y-A”
- +11.35
- TOTAL
- 772.73
- Add Cess @ 1% on “Z-A”
- +0.87
- Cost for 0.054 cum.
- 773.60
- Cost per cum
- 14,325.93
- SAY
- ₹14,325.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 244
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 244. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.