CPWD Analysis of Rates · Reinforced Cement Concrete

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.12
Analysis basis
Details of cost for 1 cum.
Priced inputs
6
Derived rate
10,585.90 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.12 Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 6 priced inputs for 1 cum and works out to ₹10,585.90 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:1 :3 in string or lacing
  • course etc
  • (NB : Rate has been taken including cost
  • of fixing in CM 1:2 as precast members are
  • to be fixesd in CM 1:2)(1 cement : 2 coarse
  • sand) as per CPWD specifications)
  • Extra labour for laying CC in RCC work
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4½.5.1 of SH:Concrete WorkRate as per item 4.5.1Sub-analysiscum110,105.1010,105.10
0114BeldarLabourday0.1736.0073.60
0101BhistiLabourday0.2816.00163.20
0123Mason 1st classMason 1st classLabourday0.04897.0035.88
0124Mason 2nd classMason 2nd classLabourday0.04816.0032.64
0128MateLabourday0.04816.0032.64
TOTAL
10,443.06
Add 1 % Water charges on “W-A”
3.38
TOTAL
10,446.44
Add GST on “X-A” (multiplying factor 0.2127)
72.60
TOTAL
10,519.04
Add 15% CPOH on “Y-A”
62.09
TOTAL
10,581.13
Add Cess @ 1% on “Z-A”
4.76
Cost for 1 cum.
10,585.89
Say
10,585.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 241. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.