Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Item number
5.12
Analysis basis
1 cum
Priced inputs
6
Derived rate
₹10,585.90/ CUM
D-01/RATE ANALYSISITEM 5.12

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.12 (Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)) is derived from 6 priced inputs for 1 cum and works out to ₹10,585.90 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:1 :3 in string or lacing
  • course etc
  • (NB : Rate has been taken including cost
  • of fixing in CM 1:2 as precast members are
  • to be fixesd in CM 1:2)(1 cement : 2 coarse
  • sand) as per CPWD specifications)
  • Extra labour for laying CC in RCC work
ANALYSIS OF RATES · ITEM 5.12DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4½.5.1 of SH:Concrete WorkRate as per item 4.5.1cum110,105.1010,105.10
0114LABBeldarday0.1736.0073.60
0101LABBhistiday0.2816.00163.20
0123LABMason 1st classMason 1st classday0.04897.0035.88
0124LABMason 2nd classMason 2nd classday0.04816.0032.64
0128LABMateday0.04816.0032.64
BUILD-UP TO RATE
TOTAL
10,443.06
Add 1 % Water charges on “W-A”
+3.38
TOTAL
10,446.44
Add GST on “X-A” (multiplying factor 0.2127)
+72.60
TOTAL
10,519.04
Add 15% CPOH on “Y-A”
+62.09
TOTAL
10,581.13
Add Cess @ 1% on “Z-A”
+4.76
Cost for 1 cum.
10,585.89
SAY
₹10,585.90
D-02/SOURCEPRINTED PAGE 241
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
241

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 241. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.