Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be measured)
- Item number
- 5.11.1
- Analysis basis
- 10 Nos
- Priced inputs
- 8
- Derived rate
- ₹384.30/ NOS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.11.1 (Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be measured) Suspended floors, roofs, landings, beams and balconies (Plan area to be measured)) is derived from 8 priced inputs for 10 Nos and works out to ₹384.30 each after water charges, GST, CPOH and cess. The full build-up is below.
- 4.8m = 288 sqm.
- Assuming that shuttering material will become unserviceable after use 40 times
- @ 25% of cost material
- Qty taken for cost using once =10x 21
- x0.85/40 = 4.463
- Qty taken for cost using once =10x
- 21x0.85/40 = 4.463
- Bracing
- MS tube 40mm
- 10x7x4.8m = 336 m
- 10x3x6.0m = 180 m
- Total = 516 m
- Qty taken for cost using once =516x0.85/40
- = 10.965
- Qty taken for cost using once =10x 21
- x0.85/40 = 4.463
- Less salvage value of material after full use
- Add 10% of cost of material for maintenance
- Deduct the rate of 3m prop
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7345 | MAT | Prop 4 m | each | 4.463 | 965.00 | 4,306.80 |
| 7343 | MAT | Adjustable telescopic prop 3 m (2.02-3.75 m) | each | -4.463 | 1,051.00 | -4,690.61 |
| 7330 | MAT | M.S. tube 40 mm dia | metre | 10.965 | 225.00 | 2,467.13 |
| 7346 | MAT | Double coupler (40x40)Double coupler | each | 4.463 | 49.00 | 218.69 |
| 9977 | MAT | Carriage | L.S. | 650 | 2.27 | 1,475.50 |
| 0116 | LAB | Fitter (grade 1) | day | 30 | 897.00 | 26,910.00 |
| 0114 | LAB | Beldar | day | 60 | 736.00 | 44,160.00 |
| 9999 | MAT | Sundries | L.S. | 1,300 | 2.27 | 2,951.00 |
- TOTAL
- 77,798.51
- Add 1 % Water charges on “W”
- +777.99
- TOTAL
- 78,576.50
- Add GST on “X” (multiplying factor 0.2127)
- +16,713.22
- TOTAL
- 95,289.72
- Add 15% CPOH on “Y”
- +14,293.46
- TOTAL
- 1,09,583.18
- Add Cess @ 1% on “Z”
- +1,095.83
- Cost for 288 sqm.
- 1,10,679.01
- Cost per sqm.
- 384.30
- SAY
- ₹384.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 240
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 240. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.