CPWD Analysis of Rates · Reinforced Cement Concrete

Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be measured)

Suspended floors, roofs, landings, beams and balconies (Plan area to be measured)

Item number
5.11.1
Analysis basis
Details of cost for 10 Nos. Room of size 6mx-
Priced inputs
8
Derived rate
384.30 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.11.1 Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be measured) Suspended floors, roofs, landings, beams and balconies (Plan area to be measured) — is derived from 8 priced inputs for 10 Nos and works out to ₹384.30 each after water charges, GST, CPOH and cess. The full build-up is below.

  • 4.8m = 288 sqm.
  • Assuming that shuttering material will become unserviceable after use 40 times
  • @ 25% of cost material
  • Qty taken for cost using once =10x 21
  • x0.85/40 = 4.463
  • Qty taken for cost using once =10x
  • 21x0.85/40 = 4.463
  • Bracing
  • MS tube 40mm
  • 10x7x4.8m = 336 m
  • 10x3x6.0m = 180 m
  • Total = 516 m
  • Qty taken for cost using once =516x0.85/40
  • = 10.965
  • Qty taken for cost using once =10x 21
  • x0.85/40 = 4.463
  • Less salvage value of material after full use
  • Add 10% of cost of material for maintenance
  • Deduct the rate of 3m prop
CodeInputUnitQuantityRate (INR)Amount (INR)
7345Prop 4 mMaterialeach4.463965.004,306.80
7343Adjustable telescopic prop 3 m (2.02-3.75 m)Materialeach-4.4631,051.00-4,690.61
7330M.S. tube 40 mm diaMaterialmetre10.965225.002,467.13
7346Double coupler (40x40)Double couplerMaterialeach4.46349.00218.69
9977CarriageMaterialL.S.6502.271,475.50
0116Fitter (grade 1)Labourday30897.0026,910.00
0114BeldarLabourday60736.0044,160.00
9999SundriesMaterialL.S.1,3002.272,951.00
TOTAL
77,798.51
Add 1 % Water charges on “W”
777.99
TOTAL
78,576.50
Add GST on “X” (multiplying factor 0.2127)
16,713.22
TOTAL
95,289.72
Add 15% CPOH on “Y”
14,293.46
TOTAL
1,09,583.18
Add Cess @ 1% on “Z”
1,095.83
Cost for 288 sqm.
1,10,679.01
Cost per sqm.
384.30
Say
384.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 240. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works