Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be measured)

Suspended floors, roofs, landings, beams and balconies (Plan area to be measured)
Item number
5.11.1
Analysis basis
10 Nos
Priced inputs
8
Derived rate
₹384.30/ NOS
D-01/RATE ANALYSISITEM 5.11.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.11.1 (Extra for additional height in centering, shuttering where ever required with adequate bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be measured) Suspended floors, roofs, landings, beams and balconies (Plan area to be measured)) is derived from 8 priced inputs for 10 Nos and works out to ₹384.30 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 4.8m = 288 sqm.
  • Assuming that shuttering material will become unserviceable after use 40 times
  • @ 25% of cost material
  • Qty taken for cost using once =10x 21
  • x0.85/40 = 4.463
  • Qty taken for cost using once =10x
  • 21x0.85/40 = 4.463
  • Bracing
  • MS tube 40mm
  • 10x7x4.8m = 336 m
  • 10x3x6.0m = 180 m
  • Total = 516 m
  • Qty taken for cost using once =516x0.85/40
  • = 10.965
  • Qty taken for cost using once =10x 21
  • x0.85/40 = 4.463
  • Less salvage value of material after full use
  • Add 10% of cost of material for maintenance
  • Deduct the rate of 3m prop
ANALYSIS OF RATES · ITEM 5.11.1DETAILS OF COST FOR 10 NOS. ROOM OF SIZE 6MX-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7345MATProp 4 meach4.463965.004,306.80
7343MATAdjustable telescopic prop 3 m (2.02-3.75 m)each-4.4631,051.00-4,690.61
7330MATM.S. tube 40 mm diametre10.965225.002,467.13
7346MATDouble coupler (40x40)Double couplereach4.46349.00218.69
9977MATCarriageL.S.6502.271,475.50
0116LABFitter (grade 1)day30897.0026,910.00
0114LABBeldarday60736.0044,160.00
9999MATSundriesL.S.1,3002.272,951.00
BUILD-UP TO RATE
TOTAL
77,798.51
Add 1 % Water charges on “W”
+777.99
TOTAL
78,576.50
Add GST on “X” (multiplying factor 0.2127)
+16,713.22
TOTAL
95,289.72
Add 15% CPOH on “Y”
+14,293.46
TOTAL
1,09,583.18
Add Cess @ 1% on “Z”
+1,095.83
Cost for 288 sqm.
1,10,679.01
Cost per sqm.
384.30
SAY
₹384.30
D-02/SOURCEPRINTED PAGE 240
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
240

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 240. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.