CPWD Analysis of Rates · Reinforced Cement Concrete
Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%)
- Item number
- 5.12A
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 6
- Derived rate
- ₹10,416.75 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.12A — Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 6 priced inputs for 1 cum and works out to ₹10,416.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- Cement concrete1:1.5:3 in string or lacing
- course etc
- (NB : Rate has been taken including cost of
- fixing in CM 1:2 as precast members are to
- be fixed in CM 1:2)(1 cement: 2 coarse sand)
- as per CPWD specifications
- LABOUR:
- Extra labour for laying CC in RCC work
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Sub AR-2 (Ref item no 4.5.1)Rate as per item Sub AR-2Sub-analysis | cum | 1 | 9,935.95 | 9,935.95 | |
| 0114 | BeldarLabour | day | 0.1 | 736.00 | 73.60 |
| 0101 | BhistiLabour | day | 0.2 | 816.00 | 163.20 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.04 | 897.00 | 35.88 |
| 0124 | Mason (brick layer) 2 nd classMason 2nd classLabour | day | 0.04 | 816.00 | 32.64 |
| 0128 | MateLabour | day | 0.04 | 816.00 | 32.64 |
- Total
- 10,273.91
- Add 1 % Water charges on “W-A”
- 3.38
- TOTAL
- 10,277.29
- Add GST on “X-A” (multiplying factor 0.2127)
- 72.60
- TOTAL
- 10,349.89
- Add 15% CPOH on “Y-A”
- 62.09
- TOTAL
- 10,411.98
- Add Cess @ 1% on “Z-A”
- 4.76
- Cost of 1 cum
- 10,416.74
- Say
- 10,416.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 242. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works