Skip to main content

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.12A
Analysis basis
1 cum
Priced inputs
6
Derived rate
₹10,416.75/ CUM
D-01/RATE ANALYSISITEM 5.12A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.12A (Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 6 priced inputs for 1 cum and works out to ₹10,416.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • Cement concrete1:1.5:3 in string or lacing
  • course etc
  • (NB : Rate has been taken including cost of
  • fixing in CM 1:2 as precast members are to
  • be fixed in CM 1:2)(1 cement: 2 coarse sand)
  • as per CPWD specifications
  • LABOUR:
  • Extra labour for laying CC in RCC work
ANALYSIS OF RATES · ITEM 5.12ADETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Sub AR-2 (Ref item no 4.5.1)Rate as per item Sub AR-2cum19,935.959,935.95
0114LABBeldarday0.1736.0073.60
0101LABBhistiday0.2816.00163.20
0123LABMason 1st classMason 1st classday0.04897.0035.88
0124LABMason (brick layer) 2 nd classMason 2nd classday0.04816.0032.64
0128LABMateday0.04816.0032.64
BUILD-UP TO RATE
Total
10,273.91
Add 1 % Water charges on “W-A”
+3.38
TOTAL
10,277.29
Add GST on “X-A” (multiplying factor 0.2127)
+72.60
TOTAL
10,349.89
Add 15% CPOH on “Y-A”
+62.09
TOTAL
10,411.98
Add Cess @ 1% on “Z-A”
+4.76
Cost of 1 cum
10,416.74
SAY
₹10,416.75
D-02/SOURCEPRINTED PAGE 242
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
242

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 242. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.