Skip to main content

CPWD Analysis of Rates · Reinforced Cement Concrete

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.12A
Analysis basis
Details of cost for 1 cum
Priced inputs
6
Derived rate
10,416.75 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.12A Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 6 priced inputs for 1 cum and works out to ₹10,416.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • Cement concrete1:1.5:3 in string or lacing
  • course etc
  • (NB : Rate has been taken including cost of
  • fixing in CM 1:2 as precast members are to
  • be fixed in CM 1:2)(1 cement: 2 coarse sand)
  • as per CPWD specifications
  • LABOUR:
  • Extra labour for laying CC in RCC work
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Sub AR-2 (Ref item no 4.5.1)Rate as per item Sub AR-2Sub-analysiscum19,935.959,935.95
0114BeldarLabourday0.1736.0073.60
0101BhistiLabourday0.2816.00163.20
0123Mason 1st classMason 1st classLabourday0.04897.0035.88
0124Mason (brick layer) 2 nd classMason 2nd classLabourday0.04816.0032.64
0128MateLabourday0.04816.0032.64
Total
10,273.91
Add 1 % Water charges on “W-A”
3.38
TOTAL
10,277.29
Add GST on “X-A” (multiplying factor 0.2127)
72.60
TOTAL
10,349.89
Add 15% CPOH on “Y-A”
62.09
TOTAL
10,411.98
Add Cess @ 1% on “Z-A”
4.76
Cost of 1 cum
10,416.74
Say
10,416.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 242. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works