Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well casing (CM) pipe of required dia, conforming to IS: 12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineer -in-charge
- Item number
- 23.3.1
- Analysis basis
- 100 metres
- Priced inputs
- 4
- Derived rate
- ₹672.30/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.3.1 (Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well casing (CM) pipe of required dia, conforming to IS: 12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineer -in-charge 100 mm nominal size dia) is derived from 4 priced inputs for 100 metres and works out to ₹672.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7758 | MAT | uPVC blind pipe 100 mm dia as per IS: 12818 | metre | 100 | 465.00 | 46,500.00 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 0115 | LAB | Coolie | day | 0.5 | 736.00 | 368.00 |
| 9999 | MAT | Sundries | L.S. | 10.07 | 2.27 | 22.86 |
- TOTAL
- 47,258.86
- Add 1 % Water charges on “W”
- +472.59
- TOTAL
- 47,731.45
- Add GST on “X” (multiplying factor 0.2127)
- +10,152.48
- TOTAL
- 57,883.93
- Add 15% CPOH on “Y”
- +8,682.59
- TOTAL
- 66,566.52
- Add Cess @ 1% on “Z”
- +665.67
- Cost of 100 metres
- 67,232.19
- Cost of 1 metre
- 672.32
- SAY
- ₹672.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1874
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1874. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.