Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level Rocky strata including Boulders
- Item number
- 23.2.2.3
- Analysis basis
- 14 metre
- Priced inputs
- 10
- Derived rate
- ₹2,496.55/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.2.2.3 (Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level Rocky strata including Boulders 400 mm dia) is derived from 10 priced inputs for 14 metre and works out to ₹2,496.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- MACHINERY :
- Extra diesel required for boring in rockystrata
- Transportation charges for to and fro to site
- (assume 140m of bore for one shifting) (2
- x30)/140
- Loading, unloading &Errection charges of drilling Rig Machine
- Extra labour to assist M/C operator &security
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0020 | MACH | Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuel | day | 0.95 | 7,850.00 | 7,457.50 |
| 1235 | MAT | Diesel oilDiesel | litre | 16 | 89.62 | 1,433.92 |
| 0005 | MACH | Hire charges of Diesel Truck - 9 tonneHire charges of Diesel Truck - 9 tonne (with POL) | day | 0.429 | 4,400.00 | 1,887.60 |
| 0114 | LAB | Beldar | day | 4 | 736.00 | 2,944.00 |
| 0130 | LAB | Mistry | day | 1 | 897.00 | 897.00 |
| 7763 | MAT | Water supply tanker of 5000 litre capacity | each | 1 | 1,625.00 | 1,625.00 |
| 0134 | LAB | Rock Hole Driller | day | 1.2 | 736.00 | 883.20 |
| 0114 | LAB | Beldar | day | 8 | 736.00 | 5,888.00 |
| 0103 | LAB | Blacksmith 2nd class | day | 1 | 816.00 | 816.00 |
| 0113 | LAB | Chowkidar | day | 1 | 736.00 | 736.00 |
- TOTAL
- 24,568.22
- Add 1 % Water charges on “W”
- +245.68
- TOTAL
- 24,813.90
- Add GST on “X” (multiplying factor 0.2127)
- +5,277.92
- TOTAL
- 30,091.82
- Add 15% CPOH on “Y”
- +4,513.77
- TOTAL
- 34,605.59
- Add Cess @ 1% on “Z”
- +346.06
- Cost for 14 metre
- 34,951.65
- Cost of 1 metre
- 2,496.55
- SAY
- ₹2,496.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1873
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1873. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.