Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level Rocky strata including Boulders
- Item number
- 23.2.2.2
- Analysis basis
- 16 metre
- Priced inputs
- 10
- Derived rate
- ₹1,955.60/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.2.2.2 (Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level Rocky strata including Boulders 350 mm dia) is derived from 10 priced inputs for 16 metre and works out to ₹1,955.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- MACHINERY :
- Extra diesel required for boring in rockystrata
- Transportation charges for to and fro to site
- (assume 140m of bore for one shifting) (2
- x30)/140
- Loading, unloading &Errection charges of drilling Rig Machine
- Extra labour to assist M/C operator &security
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0020 | MACH | Hydraulic Excavator (3D) with driver and fuel.Hydraulic Excavator (3D) with driver and fuel | day | 0.9 | 7,850.00 | 7,065.00 |
| 1235 | MAT | Diesel oilDiesel | litre | 12 | 89.62 | 1,075.44 |
| 0005 | MACH | Hire charges of Diesel Truck - 9 tonneHire charges of Diesel Truck - 9 tonne (with POL) | day | 0.429 | 4,400.00 | 1,887.60 |
| 0114 | LAB | Beldar | day | 4 | 736.00 | 2,944.00 |
| 0130 | LAB | Mistry | day | 1 | 897.00 | 897.00 |
| 7763 | MAT | Water supply tanker of 5000 litre capacity | each | 1 | 1,625.00 | 1,625.00 |
| 0134 | LAB | Rock Hole Driller | day | 1 | 736.00 | 736.00 |
| 0114 | LAB | Beldar | day | 6 | 736.00 | 4,416.00 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.75 | 816.00 | 612.00 |
| 0113 | LAB | Chowkidar | day | 1 | 736.00 | 736.00 |
- TOTAL
- 21,994.04
- Add 1 % Water charges on “W”
- +219.94
- TOTAL
- 22,213.98
- Add GST on “X” (multiplying factor 0.2127)
- +4,724.91
- TOTAL
- 26,938.89
- Add 15% CPOH on “Y”
- +4,040.83
- TOTAL
- 30,979.72
- Add Cess @ 1% on “Z”
- +309.80
- Cost for 16 metre
- 31,289.52
- Cost of 1 metre
- 1,955.60
- SAY
- ₹1,955.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1873
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1873. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.