CPWD Analysis of Rates · Rain Water Harvesting & Tube Wells

Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge

200 mm nominal size dia

Item number
23.11.3
Analysis basis
Details of cost for 30 metre
Priced inputs
6
Derived rate
2,571.05 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.11.3 Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge 200 mm nominal size dia — is derived from 6 priced inputs for 30 metre and works out to ₹2,571.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • including loading and unloading Painting with
  • anticorrosive Paint 3.14 x 0.210x30.00=20.25
  • sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
7744M.S. pipe 200 mm dia casing pipeMaterialmetre301,550.0046,500.00
7766M.S. socket 200 mm diaMaterialeach5300.001,500.00
9999Extra for making slotsMaterialL.S.1,208.052.272,742.27
Rate as per Item No.13.65.1 of SH:FinishingRate as per item 13.65.1Sub-analysissqm20.25140.252,840.06
0114BeldarLabourday1.4736.001,030.40
0130MistryLabourday0.5897.00448.50
TOTAL
55,061.23
Add 1 % Water charges on “W-A”
522.21
TOTAL
55,583.44
Add GST on “X-A” (multiplying factor 0.2127)
11,218.52
TOTAL
66,801.96
Add 15% CPOH on “Y-A”
9,594.29
TOTAL
76,396.25
Add Cess @ 1% on “Z-A”
735.56
Cost for 30 metre
77,131.81
Cost of 1 metre
2,571.06
Say
2,571.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1881. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.