Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge

200 mm nominal size dia
Item number
23.11.3
Analysis basis
30 metre
Priced inputs
6
Derived rate
₹2,571.05/ METRE
D-01/RATE ANALYSISITEM 23.11.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.11.3 (Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge 200 mm nominal size dia) is derived from 6 priced inputs for 30 metre and works out to ₹2,571.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • including loading and unloading Painting with
  • anticorrosive Paint 3.14 x 0.210x30.00=20.25
  • sqm.
ANALYSIS OF RATES · ITEM 23.11.3DETAILS OF COST FOR 30 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7744MATM.S. pipe 200 mm dia casing pipemetre301,550.0046,500.00
7766MATM.S. socket 200 mm diaeach5300.001,500.00
9999MATExtra for making slotsL.S.1,208.052.272,742.27
SUBRate as per Item No.13.65.1 of SH:FinishingRate as per item 13.65.1sqm20.25140.252,840.06
0114LABBeldarday1.4736.001,030.40
0130LABMistryday0.5897.00448.50
BUILD-UP TO RATE
TOTAL
55,061.23
Add 1 % Water charges on “W-A”
+522.21
TOTAL
55,583.44
Add GST on “X-A” (multiplying factor 0.2127)
+11,218.52
TOTAL
66,801.96
Add 15% CPOH on “Y-A”
+9,594.29
TOTAL
76,396.25
Add Cess @ 1% on “Z-A”
+735.56
Cost for 30 metre
77,131.81
Cost of 1 metre
2,571.06
SAY
₹2,571.05
D-02/SOURCEPRINTED PAGE 1881
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1881

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1881. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSRAIN WATER HARVESTING & TUBE WELLS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.