CPWD Analysis of Rates · Rain Water Harvesting & Tube Wells
Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge
200 mm nominal size dia
- Item number
- 23.11.3
- Analysis basis
- Details of cost for 30 metre
- Priced inputs
- 6
- Derived rate
- ₹2,571.05 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.11.3 — Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge 200 mm nominal size dia — is derived from 6 priced inputs for 30 metre and works out to ₹2,571.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- including loading and unloading Painting with
- anticorrosive Paint 3.14 x 0.210x30.00=20.25
- sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7744 | M.S. pipe 200 mm dia casing pipeMaterial | metre | 30 | 1,550.00 | 46,500.00 |
| 7766 | M.S. socket 200 mm diaMaterial | each | 5 | 300.00 | 1,500.00 |
| 9999 | Extra for making slotsMaterial | L.S. | 1,208.05 | 2.27 | 2,742.27 |
| Rate as per Item No.13.65.1 of SH:FinishingRate as per item 13.65.1Sub-analysis | sqm | 20.25 | 140.25 | 2,840.06 | |
| 0114 | BeldarLabour | day | 1.4 | 736.00 | 1,030.40 |
| 0130 | MistryLabour | day | 0.5 | 897.00 | 448.50 |
- TOTAL
- 55,061.23
- Add 1 % Water charges on “W-A”
- 522.21
- TOTAL
- 55,583.44
- Add GST on “X-A” (multiplying factor 0.2127)
- 11,218.52
- TOTAL
- 66,801.96
- Add 15% CPOH on “Y-A”
- 9,594.29
- TOTAL
- 76,396.25
- Add Cess @ 1% on “Z-A”
- 735.56
- Cost for 30 metre
- 77,131.81
- Cost of 1 metre
- 2,571.06
- Say
- 2,571.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1881. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works