CPWD Analysis of Rates · Rain Water Harvesting & Tube Wells
Development of tube well in accordance with IS : 2800 (part I) and IS: 11189, to establish maximum rate of useable water yield without sand content (beyond permissible limit), with required capacity air compressor, running the compressor for required time till well is fully developed, measuring yield of well by “V” notch method or any other approved method, measuring static level & draw down etc. by step draw down method, collecting water samples & getting tested in approved laboratory, including disinfection of tubewell, all complete, including hire & labour charges of air compressor, tools & accessories etc., all as per requirement and direction of Engineer-in-charge
- Item number
- 23.12
- Analysis basis
- Details of cost for 8 Hours
- Priced inputs
- 2
- Derived rate
- ₹1,085.05 / Hour
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.12 — Development of tube well in accordance with IS : 2800 (part I) and IS: 11189, to establish maximum rate of useable water yield without sand content (beyond permissible limit), with required capacity air compressor, running the compressor for required time till well is fully developed, measuring yield of well by “V” notch method or any other approved method, measuring static level & draw down etc. by step draw down method, collecting water samples & getting tested in approved laboratory, including disinfection of tubewell, all complete, including hire & labour charges of air compressor, tools & accessories etc., all as per requirement and direction of Engineer-in-charge — is derived from 2 priced inputs for 8 Hours and works out to ₹1,085.05 per hour after water charges, GST, CPOH and cess. The full build-up is below.
- MACHINERY :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0040 | Air compressor 250 cfm with two leads for pneumatic cutters/ hammersAir compressor 250 cfm with two leads for pneumatic cutters / hammersMachinery | day | 1 | 1,800.00 | 1,800.00 |
| 1235 | Diesel oilDieselMaterial | litre | 48 | 89.62 | 4,301.76 |
- TOTAL
- 6,101.76
- Add 1 % Water charges on “W”
- 61.02
- TOTAL
- 6,162.78
- Add GST on “X” (multiplying factor 0.2127)
- 1,310.82
- TOTAL
- 7,473.60
- Add 15% CPOH on “Y”
- 1,121.04
- TOTAL
- 8,594.64
- Add Cess @ 1% on “Z”
- 85.95
- Cost of 8 Hours
- 8,680.59
- Cost of 1 Hour
- 1,085.07
- Say
- 1,085.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1882. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.