Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge
- Item number
- 23.11.2
- Analysis basis
- 30 metre
- Priced inputs
- 6
- Derived rate
- ₹2,102.25/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.11.2 (Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410 plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed/ plain bevel ended pipe (type A) of required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm, including painted with outside surface with two coats of anticorrosive bitumestic paint of approved brand and manufacture, including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer -in-charge 150 mm nominal size dia) is derived from 6 priced inputs for 30 metre and works out to ₹2,102.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- including loading and unloading Painting with
- anticorrosive Paint 3.14 x.11x30.00=10.36 sqm
- including loading and unloading Painting with
- anticorrosive Paint 3.14 x.160x30.00=15.07
- sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7743 | MAT | M.S. pipe 150 mm dia casing pipe | metre | 30 | 1,250.00 | 37,500.00 |
| 7765 | MAT | M.S. socket 150 mm dia | each | 5 | 225.00 | 1,125.00 |
| 9999 | MAT | Extra for making slots | L.S. | 1,208.05 | 2.27 | 2,742.27 |
| SUB | Rate as per Item No.13.65.1 of SH:FinishingRate as per item 13.65.1 | sqm | 15.07 | 140.25 | 2,113.57 | |
| 0114 | LAB | Beldar | day | 1.4 | 736.00 | 1,030.40 |
| 0130 | LAB | Mistry | day | 0.5 | 897.00 | 448.50 |
- TOTAL
- 44,959.74
- Add 1 % Water charges on “W-A”
- +428.46
- TOTAL
- 45,388.20
- Add GST on “X-A” (multiplying factor 0.2127)
- +9,204.51
- TOTAL
- 54,592.71
- Add 15% CPOH on “Y-A”
- +7,871.87
- TOTAL
- 62,464.58
- Add Cess @ 1% on “Z-A”
- +603.51
- Cost for 30 metre
- 63,068.09
- Cost of 1 metre
- 2,102.27
- SAY
- ₹2,102.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1881
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1881. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.