Skip to main content
R/DAR 2023

Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for determining safe allowable lateral load on pile

Above 50 tonne and upto 100 tonne capacity pile
Item number
20.8.2
Analysis basis
1 test
Priced inputs
1
Derived rate
₹32,862.90/ TEST
D-01/RATE ANALYSISITEM 20.8.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.8.2 (Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for determining safe allowable lateral load on pile : Above 50 tonne and upto 100 tonne capacity pile) is derived from 1 priced inputs for 1 test and works out to ₹32,862.90 per test after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 20.8.2DETAILS OF COST FOR 1 TEST
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7253MATLateral load testing of single pile in accordance with IS : 2911 part -IV for determining safe allowable lateral load on pile. Above 50 tonne capacityLateral load testing of single pile in accordance with IS : 2911 part -IV for determining safe allowable lateral load on pile above 50 tonne capacityper test123,100.0023,100.00
BUILD-UP TO RATE
TOTAL
23,100.00
Add 1 % Water charges on “W”
+231.00
TOTAL
23,331.00
Add GST on “X” (multiplying factor 0.2127)
+4,962.50
TOTAL
28,293.50
Add 15% CPOH on “Y”
+4,244.03
TOTAL
32,537.53
Add Cess @ 1% on “Z”
+325.38
Cost per test
32,862.91
SAY
₹32,862.90
D-02/SOURCEPRINTED PAGE 1810
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1810

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1810. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.