Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for determining safe allowable lateral load on pile

Upto 50 tonne capacity pile
Item number
20.8.1
Analysis basis
1 test
Priced inputs
1
Derived rate
₹19,632.40/ TEST
D-01/RATE ANALYSISITEM 20.8.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.8.1 (Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for determining safe allowable lateral load on pile : Upto 50 tonne capacity pile) is derived from 1 priced inputs for 1 test and works out to ₹19,632.40 per test after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 20.8.1DETAILS OF COST FOR 1 TEST
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7252MATLateral load testing of single pile in accordance with IS : 2911 part -IV for determining safe allowable lateral load on pile. Upto 50 tonne capacityLateral load testing of single pile in accordance with IS : 2911 part -IV for determining safe allowable lateral load on pile up to 50 tonne capacityper test113,800.0013,800.00
BUILD-UP TO RATE
TOTAL
13,800.00
Add 1 % Water charges on “W”
+138.00
TOTAL
13,938.00
Add GST on “X” (multiplying factor 0.2127)
+2,964.61
TOTAL
16,902.61
Add 15% CPOH on “Y”
+2,535.39
TOTAL
19,438.00
Add Cess @ 1% on “Z”
+194.38
Cost per test
19,632.38
SAY
₹19,632.40
D-02/SOURCEPRINTED PAGE 1810
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1810

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1810. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.