Cyclic vertical load testing of pile in accordance with IS Code of practice IS:2911 (part IV) by Kentledge method including preparation of pile head etc for Group of two or more piles

Upto 400 tonne Safe capacity of group
Item number
20.7.2.1
Analysis basis
1 test
Priced inputs
1
Derived rate
₹40,545.15/ TEST
D-01/RATE ANALYSISITEM 20.7.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.7.2.1 (Cyclic vertical load testing of pile in accordance with IS Code of practice IS:2911 (part IV) by Kentledge method including preparation of pile head etc for Group of two or more piles Upto 400 tonne Safe capacity of group) is derived from 1 priced inputs for 1 test and works out to ₹40,545.15 per test after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 20.7.2.1DETAILS OF COST FOR 1 TEST
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7251MATCyclic verticle load testing of piles in accordance with IS : 2911 (Part-IV) including prepration of pile head etc. for Group of two piles upto 50 tonne capacity eachCyclic vertical load testing of piles in accordance with IS : 2911 (Part- IV) including preparation of pile head etc. for Group of two piles up to 50 tonne capacity eachper test128,500.0028,500.00
BUILD-UP TO RATE
TOTAL
28,500.00
Add 1 % Water charges on “W”
+285.00
TOTAL
28,785.00
Add GST on “X” (multiplying factor 0.2127)
+6,122.57
TOTAL
34,907.57
Add 15% CPOH on “Y”
+5,236.14
TOTAL
40,143.71
Add Cess @ 1% on “Z”
+401.44
Cost per test
40,545.15
SAY
₹40,545.15
D-02/SOURCEPRINTED PAGE 1810
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1810

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1810. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.