CPWD Analysis of Rates · Pile Work
Cyclic vertical load testing of pile in accordance with IS Code of practice IS:2911 (part IV) by Kentledge method including preparation of pile head etc for Group of two or more piles
Upto 400 tonne Safe capacity of group
- Item number
- 20.7.2.1
- Analysis basis
- Details of cost for 1 test
- Priced inputs
- 1
- Derived rate
- ₹40,545.15 / test
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.7.2.1 — Cyclic vertical load testing of pile in accordance with IS Code of practice IS:2911 (part IV) by Kentledge method including preparation of pile head etc for Group of two or more piles Upto 400 tonne Safe capacity of group — is derived from 1 priced inputs for 1 test and works out to ₹40,545.15 per test after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7251 | Cyclic verticle load testing of piles in accordance with IS : 2911 (Part-IV) including prepration of pile head etc. for Group of two piles upto 50 tonne capacity eachCyclic vertical load testing of piles in accordance with IS : 2911 (Part- IV) including preparation of pile head etc. for Group of two piles up to 50 tonne capacity eachMaterial | per test | 1 | 28,500.00 | 28,500.00 |
- TOTAL
- 28,500.00
- Add 1 % Water charges on “W”
- 285.00
- TOTAL
- 28,785.00
- Add GST on “X” (multiplying factor 0.2127)
- 6,122.57
- TOTAL
- 34,907.57
- Add 15% CPOH on “Y”
- 5,236.14
- TOTAL
- 40,143.71
- Add Cess @ 1% on “Z”
- 401.44
- Cost per test
- 40,545.15
- Say
- 40,545.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1810. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.