Cyclic vertical load testing of pile in accordance with IS Code of practice IS:2911 (part IV) by Kentledge method including preparation of pile head etc for Single pile

Above 50 tonne and upto 100 tonne Safe capacity pile
Item number
20.7.1.2
Analysis basis
1 test
Priced inputs
1
Derived rate
₹32,436.10/ TEST
D-01/RATE ANALYSISITEM 20.7.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.7.1.2 (Cyclic vertical load testing of pile in accordance with IS Code of practice IS:2911 (part IV) by Kentledge method including preparation of pile head etc for Single pile Above 50 tonne and upto 100 tonne Safe capacity pile) is derived from 1 priced inputs for 1 test and works out to ₹32,436.10 per test after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 20.7.1.2DETAILS OF COST FOR 1 TEST
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7250MATCyclic verticle load testing of piles in accordance with IS : 2911 (Part-IV) including prepration of pile head etc. for Single pile above 50 tonne capacity pile and upto 100 tonne capacity pileCyclic vertical load testing of piles in accordance with IS : 2911 (Part- IV) including preparation of pile head etc. for Single pile above 50 tonne capacity pile and up to 100 tonne capacity pileper test122,800.0022,800.00
BUILD-UP TO RATE
TOTAL
22,800.00
Add 1 % Water charges on “W”
+228.00
TOTAL
23,028.00
Add GST on “X” (multiplying factor 0.2127)
+4,898.06
TOTAL
27,926.06
Add 15% CPOH on “Y”
+4,188.91
TOTAL
32,114.97
Add Cess @ 1% on “Z”
+321.15
Cost per test
32,436.12
SAY
₹32,436.10
D-02/SOURCEPRINTED PAGE 1809
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1809

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1809. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSPILE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.