Skip to main content

CPWD Analysis of Rates · Pile Work

Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used

600 mm dia piles

Item number
20.2A.1
Analysis basis
Details of cost for 20 m length of pile
Priced inputs
10
Derived rate
5,386.25 / m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.2A.1 Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used 600 mm dia piles — is derived from 10 priced inputs for 20 m and works out to ₹5,386.25 per m after water charges, GST, CPOH and cess. The full build-up is below.

  • Concrete 3.14/4x0.60²x20 = 5.65 cum
  • Work supervisor
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1Sub-analysiscum5.659,504.7553,701.84
7183BentoniteBentonite of 35 kg per pileMaterialtonne0.333,050.001,006.50
9999SundriesMaterialL.S.1102.27249.70
0024Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteMachineryday0.7539,500.0029,625.00
0025Hire and running charges of light crane.Hire and running charges of light craneMachineryday0.063,900.00234.00
0026Hire and running charges of bentonite pumpMachineryday0.383,350.001,273.00
0018Hire and running charges of loaderMachineryday0.36,700.002,010.00
0017Hire and running charges of tipperMachineryday0.34,200.001,260.00
0130MistryLabourday0.12897.00107.64
0114BeldarLabourday3736.002,208.00
Total
91,675.68
Add 1% water charges on “W -A”
379.74
TOTAL
92,055.42
Add GST on “X-A” (multiplying factor 0.2127)
8,157.81
TOTAL
1,00,213.23
Add 15% CP & OH on “Y-A”
6,976.71
TOTAL
1,07,189.94
Add 1% cess on “Z -A”
534.88
Cost of 20 m pile
1,07,724.82
Cost for 1 m pile
5,386.24
Say
5,386.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1793. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works