CPWD Analysis of Rates · Pile Work
Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by percussion drilling using Direct mud circulation (DMC) or Bailer and chisel technique by tripod and mechanical Winch Machine all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tubewell boring machine shall not be used
750 mm dia piles
- Item number
- 20.2.4
- Analysis basis
- Details of cost for 15 m length of pile
- Priced inputs
- 10
- Derived rate
- ₹5,581.20 / m
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.2.4 — Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by percussion drilling using Direct mud circulation (DMC) or Bailer and chisel technique by tripod and mechanical Winch Machine all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tubewell boring machine shall not be used 750 mm dia piles — is derived from 10 priced inputs for 15 m and works out to ₹5,581.20 per m after water charges, GST, CPOH and cess. The full build-up is below.
- Concrete 3.14/4x0.75²x15 = 6.62 cum
- Work supervisor
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1Sub-analysis | cum | 6.62 | 9,504.75 | 62,921.45 | |
| 7183 | BentoniteBentonite of 35 kg per pileMaterial | tonne | 0.3 | 3,050.00 | 915.00 |
| 9999 | SundriesMaterial | L.S. | 130 | 2.27 | 295.10 |
| 0015 | Hire and running charges of Tripod and Mechanical Winch machine complete with power unit and accessoriesMachinery | day | 1.4 | 3,350.00 | 4,690.00 |
| 0025 | Hire and running charges of light crane.Hire and running charges of light craneMachinery | day | 0.06 | 3,900.00 | 234.00 |
| 0026 | Hire and running charges of bentonite pumpMachinery | day | 0.75 | 3,350.00 | 2,512.50 |
| 0018 | Hire and running charges of loaderMachinery | day | 0.3 | 6,700.00 | 2,010.00 |
| 0017 | Hire and running charges of tipperMachinery | day | 0.3 | 4,200.00 | 1,260.00 |
| 0130 | MistryLabour | day | 0.14 | 897.00 | 125.58 |
| 0114 | BeldarLabour | day | 3.5 | 736.00 | 2,576.00 |
- Total
- 77,539.63
- Add 1% water charges on “W -A”
- 146.18
- TOTAL
- 77,685.81
- Add GST on “X-A” (multiplying factor 0.2127)
- 3,140.38
- TOTAL
- 80,826.19
- Add 15% CP & OH on “Y-A”
- 2,685.71
- TOTAL
- 83,511.90
- Add 1% cess on “Z -A”
- 205.90
- Cost of 15 m pile
- 83,717.80
- Cost for 1 m pile
- 5,581.19
- Say
- 5,581.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1792. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works