Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used
- Item number
- 20.2A.2
- Analysis basis
- 15 m
- Priced inputs
- 10
- Derived rate
- ₹7,758.75/ M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.2A.2 (Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used 750 mm dia piles) is derived from 10 priced inputs for 15 m and works out to ₹7,758.75 per m after water charges, GST, CPOH and cess. The full build-up is below.
- Concrete 3.14/4x0.75²x15 = 6.62 cum
- Work supervisor
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1 | cum | 6.62 | 9,504.75 | 62,921.45 | |
| 7183 | MAT | BentoniteBentonite of 35 kg per pile | tonne | 0.3 | 3,050.00 | 915.00 |
| 9999 | MAT | Sundries | L.S. | 130 | 2.27 | 295.10 |
| 0024 | MACH | Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site | day | 0.7 | 39,500.00 | 27,650.00 |
| 0025 | MACH | Hire and running charges of light crane.Hire and running charges of light crane | day | 0.06 | 3,900.00 | 234.00 |
| 0026 | MACH | Hire and running charges of bentonite pump | day | 0.75 | 3,350.00 | 2,512.50 |
| 0018 | MACH | Hire and running charges of loader | day | 0.3 | 6,700.00 | 2,010.00 |
| 0017 | MACH | Hire and running charges of tipper | day | 0.3 | 4,200.00 | 1,260.00 |
| 0130 | LAB | Mistry | day | 0.14 | 897.00 | 125.58 |
| 0114 | LAB | Beldar | day | 3.5 | 736.00 | 2,576.00 |
- Total
- 1,00,499.63
- Add 1% water charges on “W -A”
- +375.78
- TOTAL
- 1,00,875.41
- Add GST on “X-A” (multiplying factor 0.2127)
- +8,072.81
- TOTAL
- 1,08,948.22
- Add 15% CP & OH on “Y-A”
- +6,904.02
- TOTAL
- 1,15,852.24
- Add 1% cess on “Z -A”
- +529.31
- Cost of 15 m pile
- 1,16,381.55
- Cost for 1 m pile
- 7,758.77
- SAY
- ₹7,758.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1794
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1794. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.