CPWD Analysis of Rates · New Technologies and Materials

Providing and placing “Stay in Place PVC Wall formwork” made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge. (Note: Suitable for in fill walls with appropriate Structural system)

125 mm wide Stay in Place PVC Wallform made of minimum 2.50 mm thick sections and minimum weight 21.97 kg /sqm of formwork

Item number
26.96.1
Analysis basis
Detail of cost for 20 sqm surface area
Priced inputs
6
Derived rate
2,926.70 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.96.1 Providing and placing “Stay in Place PVC Wall formwork” made up of extruded Unplasticised Poly Vinyl Chloride (uPVC) consisting of Main panel, 3 way Connector, Starter Channel, Joint Panel, Connection Panels, Door/Window frame/trim panels etc. all complete as per manufacturer design and for all heights as per direction of Engineer-in-charge. (Note: Suitable for in fill walls with appropriate Structural system) 125 mm wide Stay in Place PVC Wallform made of minimum 2.50 mm thick sections and minimum weight 21.97 kg /sqm of formwork — is derived from 6 priced inputs for 20 sqm and works out to ₹2,926.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Labour for Installation
  • Cost of Raw Materials for 20/2 = 10 sqm of
CodeInputUnitQuantityRate (INR)Amount (INR)
8996125 mm wide Stay in Place Wallform 2.50 mm thick of extruded Unplasticised Poly Vinyl Chloride (uPVC)125 mm / 165 mm wide Stay in Place Wallform 2.50 mm thick of extruded Unplasticised Poly Vinyl Chloride (uPVC).MaterialNaNNaNNaN
125 mm Wallforms @21.97 kg/sqm 219.70 kg + 5% wastage (10.98 kg) = 230.68 kgOtherkg230.68160.0036,908.80
9999Transportation ChargesMaterialL.S.610.382.271,385.56
0123Mason 1st ClassMason 1st classLabourday1897.00897.00
0115BeldarCoolieLabourday2.5736.001,840.00
9999SundriesMaterialL.S.502.27113.50
TOTAL
41,144.86
Add 1% Water charges on “W”
411.45
TOTAL
41,556.31
Add GST on “X” (multiplying factor 0.2127)
8,839.03
TOTAL
50,395.34
Add 15% CPOH on “Y”
7,559.30
TOTAL
57,954.64
Add Cess @ 1% on “Z”
579.55
Cost of 20 sqm
58,534.19
Cost for 1 sqm
2,926.71
Say
2,926.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2053. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.