Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V
- Item number
- 26.95.2
- Analysis basis
- 15 sqm
- Priced inputs
- 9
- Derived rate
- ₹1,713.55/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.95.2 (Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V Single panel for slabs with minimum weight of panel as 4.05 kg/sqm for walls with corresponding corners and jambs strips) is derived from 9 priced inputs for 15 sqm and works out to ₹1,713.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Assuming Strengthening of panels material
- (structs,bracis and propes) will become unserviceable after use of 40 times, adding for
- maintenance @ 10% of cost, taking salvage
- value after full use of material @ 30% cost.
- Telescopping to support horizantel single
- panel stay in place form work for slabs 3 m
- long adjustable telescopic propes = 36 Nos.
- Quantity for using once = 36 /40 = 0.90 No.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8995 | MAT | Single panel (Weight not less than 4.05 kg/ sqm)Single panel (Weight not less than 4.05 kg/sqm) | Sqm | 15 | 832.00 | 12,480.00 |
| 9999 | MAT | Transportation of panel | L.S. | 35.3 | 2.27 | 80.13 |
| 8724 | MAT | 12 mm thick marine plywood12 mm thick marine plywood conforming to IS: 710 | Sqm | 3.25 | 785.00 | 2,551.25 |
| 7343 | MAT | Adjustable telescopic prop 3 m (2.02 - 3.75 m)Adjustable telescopic prop 3 m (2.02-3.75 m) | each | 0.9 | 1,051.00 | 945.90 |
| 8994 | MAT | G.I binding wire | Kg | 1.5 | 66.00 | 99.00 |
| 1219 | MAT | Nails 75 mmM.S. Wire nails | Kg | 1.5 | 58.00 | 87.00 |
| 0116 | LAB | Fitter (Grade-I)Fitter (grade 1) | Day | 1.2 | 897.00 | 1,076.40 |
| 0114 | LAB | Beldar | Day | 1.2 | 736.00 | 883.20 |
| 9999 | MAT | Sundries | L.S | 23.59 | 2.27 | 53.55 |
- Add Maintenance charges @ 10% of P
- +94.59
- Deduct salvage value @ 30% of bare cost of material on P
- -283.77
- TOTAL
- 18,067.25
- Add 1 % Water charges on “W”
- +180.67
- TOTAL
- 18,247.92
- Add GST on “X” (multiplying factor 0.2127)
- +3,881.33
- TOTAL
- 22,129.25
- Add 15% CPOH on “Y”
- +3,319.39
- TOTAL
- 25,448.64
- Add Labour Cess @ 1% on “Z”
- +254.49
- Cost of 15 sqm
- 25,703.13
- Cost of 1 sqm
- 1,713.54
- SAY
- ₹1,713.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 2052
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2052. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.