Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V

Single panel for slabs with minimum weight of panel as 4.05 kg/sqm for walls with corresponding corners and jambs strips
Item number
26.95.2
Analysis basis
15 sqm
Priced inputs
9
Derived rate
₹1,713.55/ SQM
D-01/RATE ANALYSISITEM 26.95.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.95.2 (Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V Single panel for slabs with minimum weight of panel as 4.05 kg/sqm for walls with corresponding corners and jambs strips) is derived from 9 priced inputs for 15 sqm and works out to ₹1,713.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Assuming Strengthening of panels material
  • (structs,bracis and propes) will become unserviceable after use of 40 times, adding for
  • maintenance @ 10% of cost, taking salvage
  • value after full use of material @ 30% cost.
  • Telescopping to support horizantel single
  • panel stay in place form work for slabs 3 m
  • long adjustable telescopic propes = 36 Nos.
  • Quantity for using once = 36 /40 = 0.90 No.
ANALYSIS OF RATES · ITEM 26.95.2DETAILS OF COST FOR 15 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8995MATSingle panel (Weight not less than 4.05 kg/ sqm)Single panel (Weight not less than 4.05 kg/sqm)Sqm15832.0012,480.00
9999MATTransportation of panelL.S.35.32.2780.13
8724MAT12 mm thick marine plywood12 mm thick marine plywood conforming to IS: 710Sqm3.25785.002,551.25
7343MATAdjustable telescopic prop 3 m (2.02 - 3.75 m)Adjustable telescopic prop 3 m (2.02-3.75 m)each0.91,051.00945.90
8994MATG.I binding wireKg1.566.0099.00
1219MATNails 75 mmM.S. Wire nailsKg1.558.0087.00
0116LABFitter (Grade-I)Fitter (grade 1)Day1.2897.001,076.40
0114LABBeldarDay1.2736.00883.20
9999MATSundriesL.S23.592.2753.55
BUILD-UP TO RATE
Add Maintenance charges @ 10% of P
+94.59
Deduct salvage value @ 30% of bare cost of material on P
-283.77
TOTAL
18,067.25
Add 1 % Water charges on “W”
+180.67
TOTAL
18,247.92
Add GST on “X” (multiplying factor 0.2127)
+3,881.33
TOTAL
22,129.25
Add 15% CPOH on “Y”
+3,319.39
TOTAL
25,448.64
Add Labour Cess @ 1% on “Z”
+254.49
Cost of 15 sqm
25,703.13
Cost of 1 sqm
1,713.54
SAY
₹1,713.55
D-02/SOURCEPRINTED PAGE 2052
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2052

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2052. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.