CPWD Analysis of Rates · New Technologies and Materials

Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V

Single panel for slabs with minimum weight of panel as 4.05 kg/sqm for walls with corresponding corners and jambs strips

Item number
26.95.2
Analysis basis
Details of cost for 15 sqm
Priced inputs
9
Derived rate
1,713.55 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.95.2 Providing and installation of factory made Structural Stay in place form work system with double faced panels for walls, single faced panels for roof/ floor slabs, L-shaped single faced panels for corners, with necessary scaffolding, struts, bracing etc. Complete as per CPWD specification and directions of the Engineer in Charge. Design of walls and other members to be provided by the supplier & shall be duly vetted by any engineering institute of National repute such as IITs, NITs etc. and nothing extra shall be payable on this account (Additional steel reinforcement/dowels, design mix concrete of specified grade, electrical and plumbing conduits insert for services and plastering on either side of walls shall be paid for separately). Note:- This item shall be adopted for building upto G+3 Storeys only excluding seismic zone V Single panel for slabs with minimum weight of panel as 4.05 kg/sqm for walls with corresponding corners and jambs strips — is derived from 9 priced inputs for 15 sqm and works out to ₹1,713.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Assuming Strengthening of panels material
  • (structs,bracis and propes) will become unserviceable after use of 40 times, adding for
  • maintenance @ 10% of cost, taking salvage
  • value after full use of material @ 30% cost.
  • Telescopping to support horizantel single
  • panel stay in place form work for slabs 3 m
  • long adjustable telescopic propes = 36 Nos.
  • Quantity for using once = 36 /40 = 0.90 No.
CodeInputUnitQuantityRate (INR)Amount (INR)
8995Single panel (Weight not less than 4.05 kg/ sqm)Single panel (Weight not less than 4.05 kg/sqm)MaterialSqm15832.0012,480.00
9999Transportation of panelMaterialL.S.35.32.2780.13
872412 mm thick marine plywood12 mm thick marine plywood conforming to IS: 710MaterialSqm3.25785.002,551.25
7343Adjustable telescopic prop 3 m (2.02 - 3.75 m)Adjustable telescopic prop 3 m (2.02-3.75 m)Materialeach0.91,051.00945.90
8994G.I binding wireMaterialKg1.566.0099.00
1219Nails 75 mmM.S. Wire nailsMaterialKg1.558.0087.00
0116Fitter (Grade-I)Fitter (grade 1)LabourDay1.2897.001,076.40
0114BeldarLabourDay1.2736.00883.20
9999SundriesMaterialL.S23.592.2753.55
Add Maintenance charges @ 10% of P
94.59
Deduct salvage value @ 30% of bare cost of material on P
-283.77
TOTAL
18,067.25
Add 1 % Water charges on “W”
180.67
TOTAL
18,247.92
Add GST on “X” (multiplying factor 0.2127)
3,881.33
TOTAL
22,129.25
Add 15% CPOH on “Y”
3,319.39
TOTAL
25,448.64
Add Labour Cess @ 1% on “Z”
254.49
Cost of 15 sqm
25,703.13
Cost of 1 sqm
1,713.54
Say
1,713.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2052. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works